01Facts
The petitioner and respondents entered into a Joint Development Agreement dated 9 December 2015 for development of the respondents’ property into a residential apartment complex.
pp. 3–5Clause U provided for arbitration of disputes, with Bengaluru as the venue.
pp. 3–5After disputes arose, the petitioner issued a notice invoking arbitration under Section 21 of the Arbitration and Conciliation Act, 1996, on 19 May 2023. The respondents replied on 19 June 2023.
pp. 3–5The petitioner then sought appointment of a sole arbitrator under Section 11 of the Act; the respondents did not oppose the appointment but asked that the parties’ contentions remain open.
pp. 3–502Issues
i.1. Whether the parties’ disputes under the Joint Development Agreement should be referred to a sole arbitrator pursuant to Clause U.
pp. 5–6ii.2. Whether the parties’ claims and contentions should remain open for determination by the arbitrator.
pp. 5–603Law Applied
Section 11(6) of the Arbitration and Conciliation Act, 1996 empowers the Court to appoint an arbitrator where the agreed appointment process has not resulted in an appointment.
pp. 3–5Section 21 concerns commencement of arbitral proceedings upon receipt of a request to refer the dispute to arbitration.
pp. 3–5The Court relied on Clause U of the Joint Development Agreement, which provides for arbitration of disputes arising between the parties.
pp. 3–5Provisions in the judgment · 2 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 21
04Reasoning
The Court found that the Joint Development Agreement contained an arbitration clause covering disputes between the parties and that the petitioner had invoked it by issuing a notice under Section 21.
pp. 4–6In light of the clause and the invocation notice, the Court concluded that appointment of a sole arbitrator was required.
pp. 4–6The respondents’ request that their contentions remain open was addressed by expressly reserving all parties’ claims and contentions.
pp. 4–605Holding
The petition was allowed, and Hon’ble Smt. Justice Rathnakala, Former Judge of the Karnataka High Court, was appointed sole arbitrator to adjudicate the disputes at the Arbitration and Conciliation Centre (Domestic & International), Bengaluru, under that Centre’s rules.
pp. 6–7All claims and contentions were left open.
pp. 6–7The Court also directed the Registry to communicate the order and return original documents after retaining photocopies, and directed the parties to appear before the Centre’s Director on 30 November 2026 at 11:30 a.m.