01Facts
The petitioners claimed that their lands in Kenganur and Garjur villages had been used for construction of a canal for the Kenganur Yatha Neeravari project in 1980–81, without acquisition or compensation.
pp. 4, 7–8 · ¶ 2–5They relied on an Assistant Executive Engineer’s intimation confirming that the canal was constructed in that period.
pp. 4, 7–8 · ¶ 2–5Acquisition proceedings were initiated later under Section 4(1) of the Land Acquisition Act, 1894; the judgment refers to a notification dated 22 November 2011, while the petition’s prayer refers to 12 May 2011.
pp. 4, 7–8 · ¶ 2–5The petitioners sought crop compensation and damages, with interest, for the period before the notification, relying on their representation/legal notice dated 9 March 2016.
pp. 4, 7–8 · ¶ 2–5They filed this writ petition seeking a mandamus for that relief
pp. 4, 7–8 · ¶ 2–502Issues
i.1. Whether the respondents should be directed to consider the petitioners’ representation seeking crop compensation and damages, with interest, for use of their lands before acquisition proceedings were initiated
p. 8 · ¶ 7ii.2. Whether the respondents should be required to decide that representation within a specified time and report compliance to the Court
pp. 8–9 · ¶ 803Law Applied
The petition invoked Articles 226 and 227 of the Constitution of India, seeking a writ of mandamus, and relied on Section 4(1) of the Land Acquisition Act, 1894, under which the later acquisition proceedings were initiated
p. 4, 7 · ¶ 4The Court did not cite any precedent or set out a broader rule on entitlement to compensation; it directed the authorities to consider and decide the petitioners’ representation in light of the material before it
pp. 8–9 · ¶ 6–8Provisions in the judgment · 1
Land Acquisition Act, 1894 Section 4
04Reasoning
The petitioners’ claim that the lands had been used for the canal from 1980–81 was supported by the Assistant Executive Engineer’s intimation confirming the construction period and project purpose.
pp. 7–8 · ¶ 5–7In view of that document, the Court declined to accept the State’s submissions in support of its position and considered it appropriate to require the authorities to address the petitioners’ 2016 representation.
pp. 7–8 · ¶ 5–7The Court did not determine the petitioners’ entitlement to compensation or interest; it left those matters for the respondents to decide by reasoned orders
pp. 7–8 · ¶ 5–705Holding
The writ petition was disposed of with a direction to the respondents to consider the petitioners’ representation/legal notice dated 9 March 2016 seeking crop compensation, damages and interest for the period of use before acquisition proceedings, and to pass reasoned orders within four weeks.
pp. 8–9 · ¶ 7–8The respondents were also directed to file a compliance report immediately after the sixth week, on 14 December 2026
pp. 8–9 · ¶ 7–8Original Court PDF
SHRI ASHOK S/O GANGAPPA HARIJANvsTHE SPECIAL LAND ACQUISITION OFFICER
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in