Karnataka High CourtCivil Procedure and EvidenceProperty and Real Estate Law

Karnataka HC Dismisses KNNL’s Land-Acquisition Appeal After 750-Day Delay, Rejecting File-Movement Excuse

THE CHIEF ENGINEER AND ANRv.MALLAMMA W/O MALLAYYA AND ORS

Karnataka HC Dismisses KNNL’s Land-Acquisition Appeal After 750-Day Delay, Rejecting File-Movement Excuse. THE CHIEF ENGINEER AND ANR vs MALLAMMA W/O MALLAYYA AND ORS. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the appellants established sufficient cause to condone the 750-day delay in filing the appeal

The court held

The Court answered the condonation issue against the appellants

It also directed

dismissed I.A. No. 1/2023, and consequently dismissed the appeal.

01Facts

The appellants challenged the judgment and award dated 30 October 2018 in LACA No. 559/2018 by filing a miscellaneous second appeal under Section 54(2) of the Land Acquisition Act.

p. 2

The appeal was filed on 1 February 2023 with a delay of 750 days; the appellants sought condonation of delay, relying on an affidavit citing administrative processes and movement of files.

pp. 2–3

Mallamma was served but remained unrepresented.

pp. 2–3

The High Court found the affidavit bald, without relevant dates, and insufficient to explain the delay.

pp. 3, 12–13

02Issues

i.Whether the appellants established sufficient cause to condone the 750-day delay in filing the appeal

pp. 2–3, 12–13

ii.Whether administrative delay, file movement, and inter-departmental correspondence provided a satisfactory explanation for the entire period of delay

pp. 9, 12–13

03Law Applied

Section 54(2) of the Land Acquisition Act provided the basis for the appeal.

The Court applied the principles governing condonation of delay under Section 5 of the Limitation Act: the applicant must establish a reasonable, satisfactory, bona fide explanation covering the period of delay, and condonation is discretionary, not a matter of right.

pp. 3–12

Government authorities receive no special treatment and must act diligently; administrative lethargy, file movement, or bureaucratic inefficiency alone does not constitute sufficient cause.

pp. 3–12

Relying principally on Shivamma v. Karnataka Housing Board, 2025 SCC OnLine SC 1969, and State of Odisha v. Managing Committee of Namatara Girls High School, 2026 SCC OnLine SC 191, the Court emphasised that limitation serves finality and public policy, and that delay cannot be condoned merely in the asserted interest of public administration.

pp. 3–12

Provisions in the judgment · 3 · Linked ones open on LawLens

Limitation Act, 1963 Section 5Section 3

Code of Civil Procedure, 1908 Section 100

04Reasoning

The appellants’ affidavit supplied no relevant dates or account of what prevented them from filing within the prescribed period.

pp. 9, 12–13

Its general references to administrative approvals and file movement neither explained the full 750-day delay nor demonstrated continuous bona fide diligence.

pp. 9, 12–13

Applying the Supreme Court’s guidance, the Court treated the account as an excuse rather than a bona fide explanation and held that administrative delay and inter-departmental correspondence were insufficient to establish sufficient cause.

p. 9

05Holding

The Court answered the condonation issue against the appellants

p. 13

dismissed I.A. No. 1/2023, and consequently dismissed the appeal.

p. 13
Karnataka High Court

Original Court PDF

THE CHIEF ENGINEER AND ANRvsMALLAMMA W/O MALLAYYA AND ORS

Karnataka High Court · August 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment