01Facts
Suvilas Properties Pvt. Ltd. and Shriram Properties Ltd. were parties to a Joint Development Agreement and Power of Attorney concerning the “Shriram Mystique” apartment project.
pp. 6–17Disputes arose, including over e-Khata entries and registration of sale deeds, resulting in two writ petitions.
pp. 6–17During their pendency, the e-Khata was recalled and the parties reached a mediated settlement, recorded by the Court on 16 October 2026.
pp. 6–17The settlement set out the parties’ respective obligations concerning the project’s 152 apartment units, e-Khatas, payments, sale deeds and related matters.
pp. 6–17At the hearing, counsel reported substantial compliance and stated that the Greater Bengaluru Authority had opened a portal for issuing individual apartment e-Khatas.
p. 1702Issues
i.1. Whether the connected writ petitions should be disposed of in terms of the parties’ Memorandum of Settlement.
pp. 4–5, 17–18ii.2. Whether the demand drafts deposited with the Court should be handed over to Suvilas Properties’ counsel in light of the reported substantial compliance and Shriram Properties’ no-objection.
p. 1703Law Applied
The settlement was presented under Order XXIII Rule 3 of the Code of Civil Procedure, read with Articles 226 and 227 of the Constitution.
p. 6The Court’s order applies the procedure of disposing of the connected writ petitions in accordance with the parties’ settlement.
pp. 17–18The judgment does not identify or apply any separate substantive statutory rule or precedent; it records the compromise and preserves the parties’ liberty to return to Court over implementation.
pp. 17–1804Reasoning
The parties had resolved their disputes through mediation and placed detailed settlement terms before the Court.
p. 17Given counsel’s report that substantial compliance had occurred, the GBA’s portal had been opened for individual e-Khatas, and Shriram Properties did not object to release of the demand drafts, the Court disposed of the petitions in accordance with the settlement and directed release of the drafts after due procedure and compliance.
p. 17The Court did not separately analyse the underlying e-Khata or registration disputes.
p. 1705Holding
The Court disposed of both writ petitions in terms of the Memorandum of Settlement.
p. 18It directed the Registrar (Judicial) to hand over the 32 demand drafts to Suvilas Properties’ counsel after following due procedure and compliance, and reserved liberty to both parties to approach the Court if difficulties arose in implementing the compromise.
p. 18The operative order does not separately set out a distinct direction quashing the District Registrar’s communication; it disposes of the petitions by reference to the settlement.