Karnataka HC Leaves Maski-Sindhanur Bypass Contract Dispute Unresolved, Allows Contractor 10 Days to Seek Extension

M/S AMMAPUR INFRASTRUCTURE PVT LIMITEDv.UNION OF INDIA

Karnataka HC Leaves Maski-Sindhanur Bypass Contract Dispute Unresolved, Allows Contractor 10 Days to Seek Extension. M/S AMMAPUR INFRASTRUCTURE PVT LIMITED vs UNION OF INDIA. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Court should adjudicate under Article 226 the parties’ disputed claims concerning performance and termination of the Agreement.

The court held

The Court did not decide the merits of the challenge to the termination order or fresh tender.

It also directed

It disposed of the petition, reserving liberty to the parties to resolve their disputes under the Agreement’s dispute-resolution mechanism.

The petitioner could submit a representation within 10 days, which the respondents were directed to consider and decide within the following 10 days; that liberty did not establish any entitlement to an extension or revival of the Agreement.

The interim order was extended for 30 days from the date of the order.

01Facts

The petitioner entered into an Engineering, Procurement and Construction Agreement with the respondents on 20 July 2024 to construct the Maski and Sindhanur bypasses on NH 150A.

p. 2, 8

The Chief Engineer cancelled the Agreement by order dated 25 September 2025, citing the petitioner’s failure to furnish the required performance securities; a fresh tender was issued on 3 October 2025.

pp. 2–3, 6–7

The petitioner challenged both decisions, alleging that the respondents had failed to provide the required right of way and that the petitioner had subsequently submitted the additional performance security.

pp. 3–5

The respondents disputed the petitioner’s account and attributed the delay to its failure to provide the securities and proceed with the work.

pp. 6–7

The petitioner sought relief under Article 226, including an opportunity to complete the project.

p. 3, 12

02Issues

i.1. Whether the Court should adjudicate under Article 226 the parties’ disputed claims concerning performance and termination of the Agreement.

pp. 10–11

ii.2. Whether the petitioner was entitled to a direction extending or reviving the Agreement, or to another opportunity to perform it.

pp. 12–13

03Law Applied

Article 226 empowers the High Court to grant writ relief, but the Court declined to determine the parties’ contested contractual claims in writ proceedings in this case.

p. 11

The Agreement required the Authority, upon submission of the performance security, to provide at least 90% of the required right of way within 30 days (Article 3.1(iii)(a)).

p. 8

It also set out requirements for performance and additional performance security (Article 7.1(i)(a)).

pp. 9–10

Article 26 provided a contractual mechanism for dispute resolution, including conciliation and arbitration.

p. 11

No judicial precedent was cited.

04Reasoning

The parties made competing allegations about responsibility for the project’s delay: the petitioner relied on the respondents’ alleged failure to provide the required land, while the respondents relied on the petitioner’s failure to furnish security and proceed with the work.

pp. 10–11

Resolving those claims would require determining disputed contractual facts and performance obligations. Given the dispute-resolution mechanism in Article 26, the Court considered those issues unsuitable for adjudication under Article 226 and left their merits open.

p. 11

As to the petitioner’s request for an opportunity to perform the work, the Court permitted it to make a representation but expressly did not recognize any right to extension or revival of the Agreement.

pp. 12–13

05Holding

The Court did not decide the merits of the challenge to the termination order or fresh tender.

p. 11

It disposed of the petition, reserving liberty to the parties to resolve their disputes under the Agreement’s dispute-resolution mechanism.

p. 11

The petitioner could submit a representation within 10 days, which the respondents were directed to consider and decide within the following 10 days; that liberty did not establish any entitlement to an extension or revival of the Agreement.

pp. 12–13

The interim order was extended for 30 days from the date of the order.

p. 13
Karnataka High Court

Original Court PDF

M/S AMMAPUR INFRASTRUCTURE PVT LIMITEDvsUNION OF INDIA

Karnataka High Court · November 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment