01Facts
The petitioner entered into an Engineering, Procurement and Construction Agreement with the respondents on 20 July 2024 to construct the Maski and Sindhanur bypasses on NH 150A.
p. 2, 8The Chief Engineer cancelled the Agreement by order dated 25 September 2025, citing the petitioner’s failure to furnish the required performance securities; a fresh tender was issued on 3 October 2025.
pp. 2–3, 6–7The petitioner challenged both decisions, alleging that the respondents had failed to provide the required right of way and that the petitioner had subsequently submitted the additional performance security.
pp. 3–5The respondents disputed the petitioner’s account and attributed the delay to its failure to provide the securities and proceed with the work.
pp. 6–7The petitioner sought relief under Article 226, including an opportunity to complete the project.
p. 3, 1202Issues
i.1. Whether the Court should adjudicate under Article 226 the parties’ disputed claims concerning performance and termination of the Agreement.
pp. 10–11ii.2. Whether the petitioner was entitled to a direction extending or reviving the Agreement, or to another opportunity to perform it.
pp. 12–1303Law Applied
Article 226 empowers the High Court to grant writ relief, but the Court declined to determine the parties’ contested contractual claims in writ proceedings in this case.
p. 11The Agreement required the Authority, upon submission of the performance security, to provide at least 90% of the required right of way within 30 days (Article 3.1(iii)(a)).
p. 8It also set out requirements for performance and additional performance security (Article 7.1(i)(a)).
pp. 9–10Article 26 provided a contractual mechanism for dispute resolution, including conciliation and arbitration.
p. 11No judicial precedent was cited.
04Reasoning
The parties made competing allegations about responsibility for the project’s delay: the petitioner relied on the respondents’ alleged failure to provide the required land, while the respondents relied on the petitioner’s failure to furnish security and proceed with the work.
pp. 10–11Resolving those claims would require determining disputed contractual facts and performance obligations. Given the dispute-resolution mechanism in Article 26, the Court considered those issues unsuitable for adjudication under Article 226 and left their merits open.
p. 11As to the petitioner’s request for an opportunity to perform the work, the Court permitted it to make a representation but expressly did not recognize any right to extension or revival of the Agreement.
pp. 12–1305Holding
The Court did not decide the merits of the challenge to the termination order or fresh tender.
p. 11It disposed of the petition, reserving liberty to the parties to resolve their disputes under the Agreement’s dispute-resolution mechanism.
p. 11The petitioner could submit a representation within 10 days, which the respondents were directed to consider and decide within the following 10 days; that liberty did not establish any entitlement to an extension or revival of the Agreement.
pp. 12–13The interim order was extended for 30 days from the date of the order.