Karnataka High CourtAdministrative and Public LawProperty and Real Estate Law

Karnataka HC Quashes 42.9-Sq-Metre Road-Widening Surrender شرط for Bengaluru Owner’s Occupancy Certificate, Subject to Plan Check

MR. JAWAHAR. T. PINTOv.GREATER BENGALURU AUTHORITY

Karnataka HC Quashes 42.9-Sq-Metre Road-Widening Surrender شرط for Bengaluru Owner’s Occupancy Certificate, Subject to Plan Check. MR. JAWAHAR. T. PINTO vs GREATER BENGALURU AUTHORITY. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Corporation could insist on relinquishment of 42.90 sq. metres for road widening as a condition for issuing an Occupancy Certificate, where relinquishment had not been required at the sanction or commencement-certificate stage.

The court held

The petition was allowed.

It also directed

The Court quashed the 28 July 2026 endorsement insofar as it required a Relinquishment Deed for 42.90 sq. metres and directed the Assistant Director to process the Occupancy Certificate without that requirement.

The petitioner must provide a certified copy of the order within one week; the Corporation must re-verify compliance with the sanctioned plan and issue the certificate, or give reasons for refusing it on grounds other than relinquishment, within eight weeks of receiving the certified copy.

The Court clarified that the order creates no equity for the petitioner if proceedings are later initiated to acquire the relevant land.

01Facts

The petitioner, asserting ownership of property at Magrath Road, Bengaluru, applied for an Occupancy Certificate.

By endorsement dated 28 July 2026, the Assistant Director of Town Planning identified outstanding construction-related items and required the petitioner to execute a Relinquishment Deed for 42.90 sq. metres said to be required for road widening.

pp. 3–4

The petitioner submitted that the construction-related items had been completed and challenged the relinquishment requirement, contending that neither the original sanctioned plan nor the modified plan had required relinquishment.

pp. 4–5

The petitioner relied on the High Court’s order dated 10 July 2026 in W.P. No. 20839 of 2026.

p. 5

02Issues

i.1. Whether the Corporation could insist on relinquishment of 42.90 sq. metres for road widening as a condition for issuing an Occupancy Certificate, where relinquishment had not been required at the sanction or commencement-certificate stage.

pp. 4–7

ii.2. Whether the petitioner was entitled to an Occupancy Certificate without that relinquishment requirement, subject to verification of compliance with the sanctioned plan.

pp. 7–9

03Law Applied

Article 300A of the Constitution protects a person from deprivation of property except by authority of law.

p. 6

Applying its reasoning in W.P. No. 20839 of 2026 (order dated 10 July 2026), the Court stated that post facto conditions cannot be imposed where they were not required when the building licence and sanctioned plan were granted, unless a specific legal provision authorises them.

pp. 6–7

The prior order observed that no provision had been identified in the BBMP Act authorising relinquishment for road widening as a condition of building sanction, or in the GBG Act authorising that requirement at the Occupancy Certificate stage.

pp. 6–7

04Reasoning

The Court considered that relinquishment had not been required when the petitioner’s building plans were sanctioned or modified, and relied on the reasoning in W.P. No. 20839 of 2026 against imposing such a requirement after construction.

pp. 5–7

It noted that the earlier order had not been shown to have been challenged and found the same reasoning applicable to the impugned endorsement.

p. 7

The Court therefore set aside the endorsement only to the extent it required relinquishment, while preserving the Corporation’s ability to verify whether the construction complied with the sanctioned plan.

pp. 7–8

05Holding

The petition was allowed.

p. 7

The Court quashed the 28 July 2026 endorsement insofar as it required a Relinquishment Deed for 42.90 sq. metres and directed the Assistant Director to process the Occupancy Certificate without that requirement.

p. 7

The petitioner must provide a certified copy of the order within one week; the Corporation must re-verify compliance with the sanctioned plan and issue the certificate, or give reasons for refusing it on grounds other than relinquishment, within eight weeks of receiving the certified copy.

pp. 8–9

The Court clarified that the order creates no equity for the petitioner if proceedings are later initiated to acquire the relevant land.

p. 9
Karnataka High Court

Original Court PDF

MR. JAWAHAR. T. PINTOvsGREATER BENGALURU AUTHORITY

Karnataka High Court · October 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment