01Facts
The appellants challenged the judgment and award dated 27 November 2019 in LACA No. 238/2019, concerning land acquisition.
p. 2They filed the appeal on 11 April 2023 with a delay of 426 days and sought condonation by an application supported by an affidavit of the Executive Engineer.
pp. 2–3 · ¶ 2The affidavit attributed the delay principally to administrative processes and file movement.
p. 3 · ¶ 3The Court found it bald, unsupported by relevant dates, and insufficient to account for the entire period of delay.
p. 3 · pp. 13–14 · ¶ 3, 9–1002Issues
i.1. Whether the appellants established sufficient cause to condone the 426-day delay in filing the appeal
p. 3 · pp. 13–14 · ¶ 2–3, 9–10ii.2. Whether administrative delay, file movement, and inter-departmental correspondence constituted a satisfactory and bona fide explanation for the delay
p. 13 · ¶ 903Law Applied
Under Sections 3 and 5 of the Limitation Act, limitation must be applied with its statutory rigour, and delay may be condoned only where sufficient cause is established by a reasonable, satisfactory, and bona fide explanation covering the period of delay.
pp. 7–8 · pp. 13–14 · ¶ 7, 9–10In Shivamma v. Karnataka Housing Board, 2025 SCC OnLine SC 1969, the Supreme Court held that public interest does not justify routinely excusing governmental inaction; State authorities are subject to limitation and must act diligently, and administrative lethargy alone is not sufficient cause.
pp. 4–10 · ¶ 7The Court also relied on State of Odisha v. Managing Committee of Namatara Girls High School, 2026 SCC OnLine SC 191, which reiterates that condonation is discretionary and an excuse is not equivalent to an adequate explanation.
pp. 11–12 · ¶ 8Provisions in the judgment · 3 · Linked ones open on LawLens
Limitation Act, 1963 Section 5Section 3
Code of Civil Procedure, 1908 Section 100
04Reasoning
Applying these principles, the Court found that the appellants’ affidavit supplied no relevant dates or specific account of what prevented a timely appeal.
pp. 13–14 · ¶ 9–10Its reliance on file movement and administrative approvals did not explain the entire 426-day delay and amounted to an excuse rather than a bona fide explanation.
pp. 13–14 · ¶ 9–10The Court therefore found no basis to exercise its discretion to condone the delay; the merits of the appeal were not considered.
p. 1405Holding
The Court answered the issues against the appellants, dismissed I.A. No. 01/2023 seeking condonation of delay, and consequently dismissed the appeal.
p. 14Original Court PDF