Allahabad High Court
Administrative and Public LawConstitutional Law

L&T’s ₹252-crore-lower bid rejected: later suspension of debarment could not cure ineligibility on tender deadline, Allahabad High Court rules

Larsen And Toubro Limited Thru. Authorized Representative Arghya Chattopadhyay vs State Of U.P. Thru. Prin. Secy. Deptt. Of Infrastructure/Industrial Development Lko. And 5 Others

Allahabad High CourtJUDGMENT: September 29, 20263 MIN READSOURCE JUDGMENT
L&T’s ₹252-crore-lower bid rejected: later suspension of debarment could not cure ineligibility on tender deadline, Allahabad High Court rules. Larsen And Toubro Limited Thru. Authorized Representative Arghya Chattopadhyay vs State Of U.P. Thru. Prin. Secy. Deptt. Of Infrastructure/Industrial Development Lko. And 5 Others. Allahabad High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

UPEIDA invited bids for an EPC project connecting Jewar Airport to the Ganga Expressway. The bid due date was 7 September 2026.

Source reference: para. 4–19

Larsen & Toubro (L&T) submitted a bid but did not disclose that the Jal Jeevan Mission, U.P. had debarred it on 13 April 2026. On 14 September 2026, the Mission kept the debarment in abeyance.

Source reference: para. 4–19

After seeking clarification, UPEIDA declared L&T’s technical bid non-responsive on 25 September 2026 because of the debarment.

Source reference: para. 4–19

L&T challenged that decision, arguing that the RFP did not require a separate declaration of debarment, that the abeyance order removed the disqualification, and that it had been denied an opportunity to cure the issue. It also relied on its lower bid price.

Source reference: para. 4–19
02

Issues

1. Whether clause 2.1.18 of the RFP was an eligibility condition that disqualified a bidder debarred on the bid due date.

Source reference: para. 23–28

2. Whether eligibility was to be assessed on the bid due date or the date of technical evaluation, and whether the subsequent abeyance of the debarment operated retrospectively.

Source reference: para. 29–35

3. Whether the debarment-related deficiency could be cured after the bid due date, and whether UPEIDA’s rejection of L&T’s technical bid warranted judicial review under Article 226.

Source reference: para. 36–44
03

Law Applied

Under Article 226, judicial review of tender decisions concerns the legality of the decision-making process, not the merits of the tender authority’s decision; interference is warranted where the decision is arbitrary, irrational, mala fide or perverse (Tata Cellular v. Union of India; Jagdish Mandal v. State of Orissa).

Source reference: para. 20

The tender’s author is ordinarily best placed to interpret its terms, and courts defer to that interpretation unless it is unreasonable or perverse (Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corporation Ltd.; Agmatel India Pvt. Ltd. v. Resoursys Telecom).

Source reference: para. 21

Essential tender conditions must be strictly complied with and cannot be selectively waived or cured after the due date; permissible relaxation is limited to non-essential conditions and must not prejudice other bidders (Poddar Steel Corporation v. Ganesh Engineering Works; Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium)).

Source reference: para. 37–38

A stay or suspension of an order does not quash or erase it and ordinarily operates prospectively (Shree Chamundi Mopeds Ltd. v. Church of South India Trust Association).

Source reference: para. 33

Tender conditions must be applied uniformly to preserve a level playing field under Article 14.

Source reference: para. 43
04

Reasoning

Clause 2.1.18 expressly made an entity barred by a government authority on the bid due date ineligible to submit a bid. The Court treated it as an essential threshold condition, distinct from clause 2.2.2.10, which concerned the bidder’s construction record.

Source reference: para. 24–28, 39

Since the bid due date was 7 September 2026 and the Jal Jeevan Mission’s debarment remained in force on that date, L&T was ineligible. The 14 September abeyance was prospective and did not alter its status on the bid due date; the bid-validity clause did not change the date for assessing eligibility.

Source reference: para. 30–34

The clarification process gave L&T an opportunity to respond, but could not permit it to cure an essential eligibility defect through a later event. Allowing L&T to proceed would also disadvantage prospective bidders who may have abstained in reliance on the published eligibility condition.

Source reference: para. 40–44

Its lower quoted price did not create a right to have its financial bid considered, and its delayed disclosure weighed against discretionary relief, though the Court made no finding of fraud.

Source reference: para. 45–49
05

Holding

The Court held that clause 2.1.18 was an essential eligibility condition; L&T was debarred on the bid due date; and the later abeyance did not operate retrospectively.

UPEIDA’s decision to reject the technical bid was within the RFP and was not arbitrary, irrational, mala fide or perverse.

Source reference: para. 52–56

The writ petition was dismissed, with no order as to costs; interim orders were vacated.

Source reference: para. 52–56
06

Acts & Sections Cited

4 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

Fugitive Economic Offenders (Procedure for Sending Letter of Request to Contracting State) Rules, 20184

Section 1Section 2Section 3Section 4
Allahabad High Court

Original Court PDF

Larsen And Toubro Limited Thru. Authorized Representative Arghya ChattopadhyayvsState Of U.P. Thru. Prin. Secy. Deptt. Of Infrastructure/Industrial Development Lko. And 5 Others

Allahabad High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment