Facts
The petitioners’ land in Village Asarma, Surat, was acquired for the Hazira Water Project under the Land Acquisition Act, 1894. An award was published on June 26, 1990
Source reference: para. 8The petitioners filed a reference for higher compensation under Section 18 of the 1894 Act in 1993, which remained pending
Source reference: para. 9The petitioners approached the High Court in 2017 seeking a declaration that the acquisition had lapsed under Section 24(2) of the 2013 Act, asserting they remained in possession and that a neighboring plot had received a similar favorable declaration in 2016
Source reference: para. 9-10respondent records indicated that possession was taken in 1995 and compensation was tendered after the award
Source reference: para. 11-12Issues
1. Whether the land acquisition proceedings lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, despite the award being passed and possession taken decades prior to the Act’s commencement.
Source reference: para. 4-62. Whether Section 24(2) of the 2013 Act can be invoked to revive stale or concluded claims where the landowner has already sought a reference for higher compensation.
Source reference: para. 7, 17Law Applied
The Court applied the Law laid down by the Constitution Bench in Indore Development Authority v. Manoharlal and Ors. [(2020) 8 SCC 129], which interpreted Section 24(2) of the 2013 Act
Source reference: para. 2-3The rule establishes that "lapse" occurs only if neither possession has been taken nor compensation paid; if either condition is met, there is no lapse
Source reference: para. 4"paid" include tendering compensation under Section 31(1) of the 1894 Act, and the mode of taking possession is validated by the drawing of an inquest report/memorandum
Source reference: para. 5-6Section 24(2) does not revive stale or concluded proceedings or provide a new cause of action for time-barred claims
Source reference: para. 7Reasoning
The Court reasoned that the acquisition proceedings were logically concluded long before the 2013 Act came into force on January 1, 2014. Evidence showed the award was declared in 1990 and possession was taken in 1995
Source reference: para. 15The petitioners had acknowledged the finality of the acquisition by receiving the award copy in 1992 and filing a Reference for enhanced compensation under Section 18 in 1993
Source reference: para. 13, 15Following the Indore Development Authority ratio, the Court found that because the obligation to pay was fulfilled by tendering the amount and possession was taken (notwithstanding the petitioners' claims of physical occupancy), the proceedings did not lapse
Source reference: para. 5, 11The Court emphasized that Section 24(2) cannot be used as a tool to reopen concluded or stale matters from the 1990s
Source reference: para. 17Holding
The Court held that the land acquisition proceedings did not lapse under Section 24(2) of the 2013 Act as the proceedings were concluded and possession was taken as per the 1894 Act
The petition was dismissed, clarifying that previous contrary positions of the High Court were overruled by the Supreme Court's decision in Indore Development Authority. No order as to costs was made
Source reference: para. 16-17Original Court PDF
THAKORBHAI RAMUBHAI PATELvsOFFICER ON SPECIAL DUTY ( LAND ACQUISITION )
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in