Facts
The petitioner owned lands in Village Wakad, Pune, which were reserved for an octroi post in the draft development plans of 1997 and 2000
Source reference: para 2The respondent-Pimpri Chinchwad Municipal Corporation (PCMC) took possession of the land in August 2003, though a formal possession receipt (taba pavati) was executed only on February 24, 2006
Source reference: para 3, 29Formal land acquisition proceedings were delayed; a Section 6 declaration under the Land Acquisition Act, 1894 (LA Act) was issued in 2009
Source reference: para 4Following a previous High Court order in WP 2970/2013, an award was finally passed on January 22, 2015
Source reference: para 5-6The PCMC issued an order on October 10, 2016, granting rental compensation of only Rs. 3,22,308/- for the period between August 2003 and February 2006
Source reference: para 7The petitioner challenged this order, seeking rental compensation until the final payment of the award as per State policy
Source reference: para 8Issues
1. Whether the petitioner is entitled to rental compensation from the date of taking possession (August 2003) until the final payment of compensation under the award
Source reference: para 1, 352. Whether the Government Resolutions (GRs) providing for rental compensation are restricted to irrigation projects or apply to acquisitions for other public purposes like octroi posts
Source reference: para 18, 333. Whether the GR dated April 17, 2003, which cancelled previous rental compensation policies, disentitles the petitioner to relief
Source reference: para 13, 30Law Applied
The court applied the policy of the State of Maharashtra manifested in Government Resolutions dated December 1, 1972, April 2, 1979, and December 26, 2003
Source reference: para 32It relied on State of Maharashtra v. Maimuma Banu (2003) 7 SCC 448, which established that while rental compensation is not a statutory right under the LA Act, it is payable based on executive orders to compensate owners deprived of land use prior to formal acquisition
Source reference: para 20The court further applied the principle from Union of India v. Tarsem Singh (2019) 9 SCC 304, holding that discriminating between landowners based on the purpose of acquisition (e.g., irrigation vs. municipal) violates Article 14 of the Constitution
Source reference: para 33It also followed Bhagwat v. State of Maharashtra (2009) 3 Mh.L.J. 413, which clarified that even after the 2003 policy shifts, rental compensation remains payable based on the price of "open land"
Source reference: para 24Reasoning
The court found that PCMC's own order admitted taking possession in August 2003, negating their argument that the period should be restricted
Source reference: para 29It rejected the respondents' contention that rental compensation only applies to irrigation projects, reasoning that the core issue is the deprivation of the owner's enjoyment of land, regardless of the ultimate public use
Source reference: para 33-34Although the GR dated April 17, 2003, initially cancelled the 1972 and 1979 schemes, the court interpreted the subsequent GR of December 26, 2003, as a continuation of the entitlement, albeit with a modified calculation basis—8% p.a. on the value of "open land" rather than the total award value
Source reference: para 32, 35The court distinguished the precedent in Ashok v. Masu Bansode, noting that the present case was governed by the 1894 Act and State policy, whereas Ashok dealt with the 2013 Act where additional statutory compensation for private negotiation is already provided
Source reference: para 37Holding
The court allowed the writ petition and quashed the impugned order of October 10, 2016
It held that the petitioner is entitled to rental compensation from August 2003 until the date the compensation under the 2015 award was actually paid
Source reference: para 40(b)The court directed PCMC to calculate this amount at the rate of 8% p.a. on the price/value of "open land" as per the GR dated December 26, 2003
Source reference: para 40(b)Additionally, the court awarded interest at 6% p.a. on the delayed rental compensation
Source reference: para 40(c)The respondents were ordered to complete the determination and payment within four months, adjusting for amounts already paid
Source reference: para 40(d)-(e)Original Court PDF
M/S. DEVI CONSTRUCTION COMPANYvsTHE STATE OF MAHARASHTRA THROUGH PRINCIPAL SECRETARY, URBAN DEVELOPMENT DEPT. AND ORS.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in