Punjab and Haryana High Court
Property and Real Estate LawAdministrative and Public Law

Landowners are entitled to solatium and interest on compensation for acquisitions under the National Highways Act.

Brij Kishore Goel vs Union Of India And Ors

Punjab and Haryana High CourtJUDGMENT: September 08, 20263 MIN READSOURCE JUDGMENT
Landowners are entitled to solatium and interest on compensation for acquisitions under the National Highways Act.. Brij Kishore Goel vs Union Of India And Ors. Punjab and Haryana High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner and petitioners in 55 connected writ petitions were landowners whose land had been acquired under the National Highways Act, 1956. They sought payment of statutory solatium under Section 23(2) of the Land Acquisition Act, 1894, together with interest on the solatium

Source reference: p.4, para.2

The Court had earlier directed the petitioners to file affidavits confirming non-payment of solatium and directed the competent authority/NHAI to verify entitlement and process payment of the undisputed principal amount. The question of interest had initially been kept open because review proceedings were pending before the Supreme Court

Source reference: pp.5–6, para.3

At the hearing, NHAI stated that it did not dispute its liability to pay solatium and interest in accordance with Union of India v. Tarsem Singh, (2019) 9 SCC 304, and National Highways Authority of India v. Tarsem Singh, 2025 SCC OnLine SC 235. NHAI further stated that solatium had already been paid in some cases and would be paid in the remaining cases upon receipt of the Collector’s calculations

Source reference: p.7, para.4
02

Issues

Whether landowners whose land was acquired under the National Highways Act, 1956 are entitled to statutory solatium under Section 23(2) of the Land Acquisition Act, 1894

Source reference: pp.5–7, paras.3–4

Whether the landowners are entitled to interest on the amount of solatium

Source reference: pp.5–7, paras.3–5

What directions should be issued for calculation and disbursement of solatium and interest in the connected cases

Source reference: p.7, para.5
03

Law Applied

The Court applied Section 23(2) of the Land Acquisition Act, 1894, which provides for statutory solatium on the market value of acquired land.

Source reference: p.5, para.3

It relied principally on Union of India v. Tarsem Singh, (2019) 9 SCC 304, holding that landowners whose property is acquired under the National Highways Act, 1956 are entitled to solatium under Section 23(2) of the 1894 Act

Source reference: p.5, para.3

The Court also relied on National Highways Authority of India v. Tarsem Singh, 2025 SCC OnLine SC 235, in relation to the liability of the acquiring authority to pay solatium and applicable interest

Source reference: p.7, para.4

The competent Land Acquisition Collector is responsible for calculating the amounts payable, while NHAI is required to release payment after receiving the calculation

Source reference: p.7, para.5
04

Reasoning

The entitlement to solatium was no longer a disputed legal question in view of the Supreme Court’s decisions in Tarsem Singh. NHAI expressly accepted its liability for solatium and interest, thereby eliminating the need for adjudication of individual entitlement at the writ stage

Source reference: p.7, para.4

Since the principal amounts and interest had to be determined case-wise on the basis of the acquisition records, the Court directed the Land Acquisition Collector to calculate the amounts payable in each case. The Court consequently adopted a time-bound administrative mechanism: the Collector was to complete the calculations within two months, after which NHAI was to release payment within four weeks

Source reference: p.7, para.5
05

Holding

The Court held that the landowners were entitled to statutory solatium under Section 23(2) of the Land Acquisition Act, 1894, along with applicable interest, in respect of acquisitions under the National Highways Act, 1956

All the writ petitions were disposed of in view of NHAI’s statement. The concerned Land Acquisition Collector was directed to calculate solatium and interest within two months from the date of the order and intimate the amount to NHAI. NHAI was directed to release payment within four weeks of receiving the calculations. Petitioners dissatisfied with the calculation were left at liberty to pursue remedies available in law

Source reference: p.7, para.5

Pending applications, if any, were also disposed of

Source reference: p.7, para.6
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

National Highways Act, 19561

Section 23
Punjab and Haryana High Court

Original Court PDF

Brij Kishore GoelvsUnion Of India And Ors

Punjab and Haryana High Court · September 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment