Bombay High Court

Legal Headline: Section 9 jurisdiction is limited to preserving the subject-matter of the arbitration agreement between the parties.

Rupji Constructions vs Municipal Corporation Of Greater Mumbai (Mcgm) (Org Resp No 2)

Bombay High CourtJUDGMENT: April 29, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner Society entered into a Development Agreement (DA) in 2013 for property redevelopment with the Respondent Developer

Source reference: para. 3

Following defaults in statutory dues, corpus payments, and transit rent, the Society filed a Section 9 Petition in 2017 seeking interim protection

Source reference: para. 4

On December 14, 2017, the Court attached various personal assets of the partners and issued a blanket injunction against the Developer from alienating any properties across all their projects

Source reference: para. 30, 32

Subsequently, thirty-one interim applications were filed by third parties (allottees/tenants from unrelated projects and family members) seeking to recover dues or intervene in the proceedings

Source reference: paras. 11-14

An Arbitral Tribunal was finally constituted in September 2024, and a Section 17 Order was passed in February 2026

Source reference: para. 5, 7
02

Issues

1. Whether a Section 9 Court preserves jurisdiction to entertain applications from third parties who are not signatories to the arbitration agreement

Source reference: paras. 20-21

2. Whether the Court should continue exercising jurisdiction under Section 9 once an Arbitral Tribunal has been constituted and has passed orders under Section 17

Source reference: paras. 22, 24

3. Whether blanket injunctions affecting unrelated projects should be maintained or relegated to the Arbitral Tribunal for reconsideration

Source reference: paras. 34, 39
03

Law Applied

The Court applied Section 9 and Section 17 of the Arbitration and Conciliation Act, 1996, noting that the jurisdiction is limited to "parties" as defined under Section 2(1)(h) for the preservation of the "subject-matter of the arbitration agreement"

Source reference: paras. 19-21

The Court relied on the principle from Firm Ashok Traders v. Gurumukh Das Saluja regarding the necessity of a manifest intent to arbitrate

Source reference: para. 23

The Court integrated the doctrine of "veritable parties" or "non-signatories" as established in Cox and Kings Ltd. v. SAP India (P) Ltd., ASF Buildtech v. Shapoorji Pallonji, and Adavya Projects v. Vishal Structurals, which requires a non-signatory to show demonstrable proximity, consent, or a de facto connection to the dispute to be impleaded

Source reference: paras. 27-28
04

Reasoning

The Court reasoned that Section 9 is not a standalone equity jurisdiction but is strictly aid-of-arbitration; therefore, the Society is the only "protectee" under this specific DA

Source reference: para. 21

The Court found that third-party decree-holders from unrelated projects lack privity and cannot "shoo-in" to Section 9 proceedings to execute money decrees obtained in other forums

Source reference: paras. 27, 41

Regarding the continuation of the December 2017 blanket injunction, the Court observed that under Section 9(3), once a Tribunal is formed, the Court must refrain from entertaining applications unless Section 17 is inefficacious

Source reference: para. 22

The Court concluded that since the Society’s claims (damages of ~Rs. 18.65 Crores) are now before the Tribunal, the Tribunal is the proper forum to assess whether the security currently held in Court (over Rs. 11 Crores) is sufficient or surplus

Source reference: paras. 34-37
05

Holding

The Court disposed of the Section 9 Petition and all 31 Interim Applications and held that third parties with no privity have no standing to intervene

The Court directed: (i) the Arbitral Tribunal to assess within three months the amount required to secure the Society's claim; (ii) any surplus funds to be released to the Developer, subject to orders from other competent execution courts; (iii) Respondent partner Tejal Rupji to honor his undertaking to clear third-party decrees within 12 months of such release; and (iv) the Court Commissioner to handover all materials to an official Registry-designated Commissioner and be paid fees of Rs. 2,50,000

Source reference: para. 70(C), 70(D), 70(F), 70(G)
Bombay High Court

Original Court PDF

Rupji ConstructionsvsMunicipal Corporation Of Greater Mumbai (Mcgm) (Org Resp No 2)

Bombay High Court · April 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment