Facts
In 2006, Reliance Industries Limited ("Petitioner") was leased Plot No. C-64 in Bandra-Kurla Complex (BKC) for 80 years to construct a Convention Centre and Commercial Complex
Source reference: para. 5The Lease Deed stipulated construction completion within four years (by August 2010), failing which additional premium/penalty would apply
Source reference: para. 6Subsequently, the Petitioner was allotted additional built-up area via a Supplementary Lease Deed in 2007 and further allotments in 2012, totaling 3,12,500 sq. mtrs.
Source reference: paras. 8, 15Construction was delayed due to: (i) an interim injunction by the High Court (2007–2012) affecting the integrated project
Source reference: para. 9, 14Construction was delayed due to: (ii) the time required for statutory clearances (environmental, aviation, etc.)
Source reference: para. 16Construction was delayed due to: (iii) the fact that the full Commencement Certificate (CC) for the composite structure was only issued on April 16, 2014
Source reference: para. 18MMRDA issued a demand notice on September 12, 2017, for additional premium/penalty for a delay of 7 years and 12 days
Source reference: para. 3, 22The Petitioner paid ₹646.77 Crores under protest and furnished a Bank Guarantee of ₹1312.54 Crores to obtain a part Occupation Certificate
Source reference: para. 25, 85Issues
1. Whether the Writ Petition is maintainable given the contractual nature of the dispute and the existence of an alternative remedy under Section 44 of the MMRDA Act
Source reference: para. 28, 462. Whether the demand for additional premium/penalty is valid considering the court stay, the issuance of the Commencement Certificate only in 2014, and MMRDA’s representation that no time limit applied to additional area
Source reference: para. 33-363. Whether the MMRDA’s 2015 policy extending the construction period from four to six years should apply uniformly to the Petitioner under Article 14 of the Constitution
Source reference: para. 38, 954. Whether the undertaking and payment made by the Petitioner preclude it from seeking a refund
Source reference: para. 85, 92Law Applied
The court applied Article 14 of the Constitution of India, emphasizing that state actions, even in contractual matters, must be non-arbitrary and fair
Source reference: para. 46, 53It relied on the Doctrine of Promissory Estoppel from Motilal Padampat Sugar Mills Co. Ltd. v. State of U.P., holding that the state cannot resile from promises that induced a party to alter its position
Source reference: para. 76Under Section 72 of the Indian Contract Act, the court affirmed that payments made under coercion or duress (to save property or legal rights) are recoverable
Source reference: para. 87-91It further applied the principle of Judicial Discipline, following the coordinate bench decision in Raghuleela Builders Pvt. Ltd. v. MMRDA, which held that discriminatory application of time-extension policies violates Article 14
Source reference: para. 95-98Reasoning
The Court reasoned that the construction was "composite and unseverable" in nature; thus, the original four-year timeline became commercially and legally impossible to meet once the built-up area was nearly tripled and the project was stayed by the Court
Source reference: para. 70, 72Crucially, Article 2(c) of the Lease Deed prohibited work until plans were approved; since the effective Commencement Certificate for the expanded project was only issued in 2014, the timeline could not logically run from 2006
Source reference: para. 65, 77The Court found that MMRDA had expressly promised in 2011/2012 to exclude the stay period and stated there would be "no time limit" for the additional area, creating a promissory estoppel
Source reference: para. 74-76Furthermore, the MMRDA's 2015 resolution extending the completion period to six years for new lessees was held to be discriminatory; all BKC lessees face similar statutory hurdles and must be treated equally
Source reference: para. 95-97Finally, the Court dismissed the "undertaking" defense, noting the payment was made under "coercion and duress" to avoid lease termination and to secure an Occupation Certificate, which does not constitute voluntary waiver
Source reference: para. 86, 93Holding
The Court allowed the Writ Petition and set aside the demand notices dated September 12, 2017, and June 13, 2019
It held that the Petitioner was entitled to a six-year completion period (per the 2015 policy) plus the period of the court stay (4 years, 4 months, 26 days) from the date of the effective CC in 2014
Source reference: para. 100MMRDA is ordered to refund ₹646,77,68,594/- within 90 days, failing which interest will apply at the rate stipulated in the Lease Agreement
Source reference: para. 103All related Bank Guarantees, including the one for ₹1312.54 Crores, shall remain valid for only 90 days from the order date
Source reference: para. 104Rule was made absolute
Source reference: para. 105Original Court PDF
Reliance Industries Ltd. And Anr.vsThe Mumbai Metropolitan Region Development Authority (Mmrda) And 2 Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in