Madhya Pradesh High CourtCivil Procedure and EvidenceCivil Law

### Liberal Construction of "Sufficient Cause" for Condonation of Delay Must Advance Substantial Justice

State Of M.P.v.Ram Bharosey

### Liberal Construction of "Sufficient Cause" for Condonation of Delay Must Advance Substantial Justice. State Of M.P. vs Ram Bharosey. Madhya Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the learned Appellate Court erred in dismissing the appeal on the ground of limitation without properly appreciating the explanation furnished for the delay?

The court held

The High Court answered the substantial question of law in favor of the appellant

It also directed

It held that the First Appellate Court erred in its refusal to condone the delay. The Court allowed the Section 5 application, condoned the delay, set aside the judgment dated 16.07.2009, and remanded the matter to the First Appellate Court for a decision on the merits

The records were ordered to be sent back immediately

01Facts

The State of Madhya Pradesh (appellant) filed a first appeal on 29.01.2009 challenging a judgment and decree dated 16.10.2008 passed by the Civil Judge, Class-I, Guna

¶ 5

Along with the appeal, the State filed an application under Section 5 of the Limitation Act to condone the delay. The delay was attributed to the Officer-in-Charge being occupied with election duties (30.11.2008 to 08.12.2009) and the Principal of the college being occupied with university examinations (15.12.2008 to 21.12.2009)

¶ 6

The First Appellate Court dismissed the appeal solely on the ground of limitation

¶ 1

The appellant then preferred this Second Appeal before the High Court.

02Issues

i.1. Whether the learned Appellate Court erred in dismissing the appeal on the ground of limitation without properly appreciating the explanation furnished for the delay?

¶ 3

03Law Applied

The court applied Section 5 of the Limitation Act, 1963, regarding the condonation of delay upon showing "sufficient cause"

¶ 5, 7

The court relied heavily on the precedent Ram Nath Sao vs. Gobardhan Sao (2002) 3 SCC 195, which established that the expression "sufficient cause" should receive a liberal construction to advance substantial justice

¶ 8

The principle dictates that acceptance of an explanation for delay should be the rule and refusal an exception, provided there is no negligence, inaction, or lack of bona fides

¶ 8

Provisions in the judgment · 2 · Linked ones open on LawLens

Limitation Act, 1963 Section 5

Code of Civil Procedure, 1908 Section 22

04Reasoning

The High Court found that the First Appellate Court adopted a pedantic approach and failed to properly appreciate the specific reasons provided by the State

¶ 7

The Court noted that the appellant (a College Principal) provided clear reasons for the delay, including election duties and examination oversight

¶ 6, 9

Following the Supreme Court's mandate in Ram Nath Sao, the Court reasoned that since no negligence or lack of bona fides was imputable to the appellant, and because high stakes or arguable points of law were involved, the technicality of limitation should not defeat the right to a decision on merits

¶ 8-9

The Court concluded that the "sufficient cause" requirement was satisfied

¶ 9

05Holding

The High Court answered the substantial question of law in favor of the appellant

¶ 10

It held that the First Appellate Court erred in its refusal to condone the delay. The Court allowed the Section 5 application, condoned the delay, set aside the judgment dated 16.07.2009, and remanded the matter to the First Appellate Court for a decision on the merits

¶ 10

The records were ordered to be sent back immediately

¶ 11
Madhya Pradesh High Court

Original Court PDF

State Of M.P.vsRam Bharosey

Madhya Pradesh High Court · July 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment