Facts
The Petitioner, a construction company, was awarded a contract by the Respondent (CPWD) for the construction of the IIM Jammu campus.
Source reference: para. 6(b)Disputes arose regarding project delays, defects, and payments after the campus was inaugurated in 2024.
Source reference: para. 6(f)-(g)The Petitioner invoked the arbitration clause (Clause 25 of the GCC) and filed a Section 11 petition for the appointment of an arbitrator, alongside three Section 9 petitions for interim protection against coercive actions.
Source reference: para. 6(h)-(k)During proceedings, IIM Jammu (the ultimate beneficiary) sought impleadment.
Source reference: para. 6(l)The Joint Registrar allowed impleadment on 23.01.2026.
Source reference: para. 6(m)The Petitioner challenged this via Chamber Appeals, which were filed with a one-day delay.
Source reference: para. 6(p)The Division Bench remanded the matter to the Single Judge to first decide the condonation of delay and then the merits of the impleadment.
Source reference: para. 6/pIssues
1. Whether the one-day delay in filing Chamber Appeals under Chapter II Rule 5 of the Delhi High Court (Original Side) Rules, 2018 is condonable under Section 5 of the Limitation Act, 1963.
Source reference: para. 462. Whether IIM Jammu, as a non-signatory and ultimate beneficiary of the contract, is a necessary or proper party to be impleaded in the arbitration proceedings.
Source reference: para. 82Law Applied
Section 5 of the Limitation Act, 1963, regarding the condonation of delay upon showing "sufficient cause".
Source reference: para. 33Interpretation of Chapter II Rule 5 of the Delhi High Court (Original Side) Rules, 2018, noting the absence of restrictive language like "but not thereafter".
Source reference: para. 63-65The court applied the "Group of Companies" doctrine and principles of party autonomy under Sections 7 and 11 of the Arbitration and Conciliation Act, 1996.
Source reference: para. 90Reliance on Cox and Kings Ltd. v. Sap India Pvt. Ltd., establishing that a non-signatory is bound only if it consented to be bound or acted as a "veritable party".
Source reference: para. 94Reliance on Duro Felguera, S.A. v. Gangavaram Port Ltd., which confines the court’s Section 11 jurisdiction to examining the existence of an arbitration agreement between specific parties.
Source reference: para. 90Reasoning
Regarding the delay, the Court rejected the argument that the Delhi High Court (Original Side) Rules exclude the Limitation Act. Since the Rules do not contain a peremptory bar (unlike provisions for written statements), Section 5 remains applicable to advance "substantial justice".
Source reference: para. 57, 66Regarding impleadment, the Court found that the contract was strictly between CPWD and the Petitioner.
Source reference: para. 83The fact that IIM Jammu was the "ultimate beneficiary" or provided funding does not create privity of contract.
Source reference: para. 84, 94The Court noted that Clause 36 of the NIT required IIM Jammu to communicate deficiencies through CPWD, preserving CPWD as the sole nodal contractual authority.
Source reference: para. 97-98Impleading every project beneficiary would destroy party autonomy and convert focused arbitrations into sprawling multi-party disputes.
Source reference: para. 95CPWD’s attempt to nominate an arbitrator without the mandatory qualifications (Graduate Engineer) stipulated in Clause 25 was found to violate the agreed terms.
Source reference: para. 111-114Holding
The Court allowed the applications for condonation of delay, holding that a one-day delay is minimal and justifiable.
It allowed the Chamber Appeals and set aside the impleadment of IIM Jammu, ruling that it was neither a signatory nor a veritable party to the arbitration agreement.
Source reference: para. 102-103The Section 11 petition was allowed, directing CPWD to appoint a nominee arbitrator as per the mandatory qualifications in Clause 25 within 15 days.
Source reference: para. 116-118The Section 9 petitions were converted into Section 17 applications to be decided by the newly constituted Arbitral Tribunal.
Source reference: para. 122-126Acts & Sections Cited
12 provisions across 4 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19967
Code of Civil Procedure, 19083
Limitation Act, 19631
Delhi High Court Act, 19661
Original Court PDF
M/S Ramacivil India Construction Pvt Ltd Through Its Authorized Representative Director Sh R N GuptavsCentral Public Works Department Through Its Addl Director General
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
