Facts
The Appellant invited bids for construction of a Disaster Management and Training Centre at Rajokari, New Delhi. The Respondent’s bid was accepted for a tendered value of ₹3,73,98,625, with the work scheduled for completion within 120 days from 12 November 2014.
Source reference: para. 4Although the Respondent commenced work on 12 November 2014, the work was completed on 7 March 2016, when a Completion Certificate was issued while reserving the Appellant’s right to claim delay damages.
Source reference: para. 5The Respondent subsequently sought extension of time, which was granted on 9 January 2017 subject to protest. The final bill was submitted on 31 January 2018, although the contract required it to be submitted within the stipulated period following physical completion or the Final Certificate of Completion.
Source reference: para. 5Under Clause 25 of the GCC, disputes were required to pass through successive stages involving the Superintendent Engineer, Chief Engineer and Dispute Redressal Committee before arbitration could be invoked.
Source reference: para. 6The Respondent raised claims in 2019 and ultimately requested appointment of an arbitrator on 15 November 2019.
Source reference: para. 7The Arbitral Tribunal awarded ₹1,42,06,630 in favour of the Respondent.
Source reference: para. 8In proceedings under Section 34 of the Arbitration and Conciliation Act, 1996, the Commercial Court partly set aside the award concerning Watch and Ward Expenses but upheld the remaining claims and the finding on limitation.
Source reference: paras. 1–2, 9The Appellant challenged the decision under Section 37, with limitation being the sole surviving issue.
Source reference: para. 2Issues
Whether the Respondent’s claim and invocation of arbitration were barred by limitation on the ground that limitation commenced from the date of completion of work, namely 7 March 2016, or from the date stipulated for submission of the final bill?
Source reference: paras. 11, 16–20Whether Article 18 of the Schedule to the Limitation Act, 1963, or Article 137 thereof governed the limitation period for the Respondent’s application for appointment of an arbitrator?
Source reference: paras. 17–20Whether the contractual dispute-resolution procedure under Clause 25 of the GCC postponed the accrual of the Respondent’s right to apply for appointment of an arbitrator until completion of the prescribed pre-arbitration steps?
Source reference: paras. 6, 18–20Law Applied
The Court exercised its jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, while examining the limitation issue arising from the award and the Section 34 judgment.
Source reference: paras. 1–2Article 18 of the Schedule to the Limitation Act, 1963, ordinarily prescribes limitation for a suit relating to the price of work done, commencing when the work is done; however, the Court held that it was inapplicable where the contractual completion period was subsequently extended and the right to seek appointment of an arbitrator arose only after compliance with a multi-stage contractual dispute-resolution mechanism.
Source reference: para. 17Article 137, which provides a three-year period from the date when the right to apply accrues, governed the application for appointment of an arbitrator.
Source reference: para. 19Where the contract makes prior administrative or dispute-resolution steps conditions precedent to arbitration, the cause of action for seeking appointment of an arbitrator does not accrue until those steps have been completed.
Source reference: paras. 18–20Reasoning
The Court rejected the Appellant’s contention that limitation commenced on 7 March 2016, the date of physical completion, or on 7 April 2016, the date asserted by the Appellant under Clause 9 of the GCC.
Source reference: paras. 11, 16The Respondent’s request for extension of time was approved on 9 January 2017, and the final bill was thereafter submitted on 31 January 2018; moreover, the Appellant had not prepared the final bill despite its obligation to do so if the Respondent failed to submit one.
Source reference: paras. 14, 16–17More importantly, Clause 25 required the Respondent to pursue successive remedies before the Superintendent Engineer, Chief Engineer and DRC before requesting appointment of an arbitrator.
Source reference: paras. 6, 18–19Since the right to apply for appointment of an arbitrator arose only after the contractual procedure had been followed, Article 18 could not be applied by treating completion of the work as the starting point.
Source reference: paras. 19–20The Court therefore applied Article 137 and held that the Respondent’s right to seek appointment of an arbitrator accrued only upon completion of the prescribed contractual stages.
Source reference: paras. 19–20Holding
The Court held that the Respondent’s invocation of arbitration was not barred by limitation.
The limitation period did not commence from 7 March 2016, the date of completion of the work, because the completion period had subsequently been extended and Clause 25 required compliance with a contractual pre-arbitration dispute-resolution mechanism.
Source reference: paras. 16–20Article 137, rather than Article 18, governed the limitation applicable to the application for appointment of an arbitrator.
Source reference: paras. 19–20Finding no merit in the appeal, the Court dismissed FAO (COMM) 340/2025 and closed the pending applications.
Source reference: paras. 21–22Acts & Sections Cited
4 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Limitation Act, 19632
Original Court PDF
Delhi Tranporation And Tourism Developlment CorporationvsSunehari Bagh Builders Pvt. Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
