Limitation for executing a pre-2015 award under Article 136 runs from 23.10.2015, excluding the automatic-stay period.

SOUTH EASTERN COALFIELDS LIMITEDv.M/S SHYAM LAL AGRAWAL CONTRACTOR

Limitation for executing a pre-2015 award under Article 136 runs from 23.10.2015, excluding the automatic-stay period.. SOUTH EASTERN COALFIELDS LIMITED vs M/S SHYAM LAL AGRAWAL CONTRACTOR. Chhattisgarh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the 12-year period under Article 136 for executing an award, where the Section 34 challenge was pending before 23.10.2015, runs from the date of the award or from 23.10.2015, when the amended Section 36 took effect.

The court held

The Court holds that the period for executing the award runs from 23.10.2015, when amended Section 36 became operative, and not from the date of the award, because enforcement was legally barred during the pendency of the Section 34 proceedings under the then-binding NALCO line of authority.

It also directed

The execution application filed on 16.09.2025 is therefore within limitation under Article 136, and the objection is rejected.

The writ petition under Article 227 is dismissed, and the Commercial Court's order dated 08.09.2026 in Execution Case No. 30/2025 is upheld.

01Facts

The Arbitral Tribunal passed an award on 25.02.2011 in favour of the respondent (award-holder) for Rs. 45,55,543/- with interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, and costs of Rs. 1,21,600/-

¶ 2

The petitioners (award-debtors) challenged the award under Section 34, which was dismissed on 18.04.2017

¶ 2

They appealed under Section 37 on 30.06.2017, and the appeal was dismissed for want of prosecution on 17.06.2025

¶ 2

The respondent filed Execution Case No. 30/2025 on 16.09.2025 before the Commercial Court, Nava Raipur

¶ 2

The petitioners objected that execution was barred under Article 136 of the Limitation Act, 1963

¶ 2

The Commercial Court excluded the period from 25.02.2011 to 23.10.2015 (4 years, 7 months, 28 days) and held the execution within limitation by order dated 08.09.2026

¶ 2–3

The petitioners computed expiry of limitation as 24.02.2023

¶ 3

They challenged the order under Article 227 of the Constitution

The petition was argued against the earlier order of this Court in WP 590/2026 (decided 14.05.2026) on an identical issue

¶ 5, 7

02Issues

i.1. Whether the 12-year period under Article 136 for executing an award, where the Section 34 challenge was pending before 23.10.2015, runs from the date of the award or from 23.10.2015, when the amended Section 36 took effect.

¶ 5 (quoting WP 590/2026 · ¶ 11, 24, 33) · ¶ 7

ii.2. Whether the mere pendency of Section 34 proceedings operated as an automatic stay on enforcement under the unamended Section 36, so as to render the award unenforceable until 23.10.2015.

¶ 5 (quoting WP 590/2026 · ¶ 13, 24, 27)

iii.3. Whether the execution petition filed on 16.09.2025 is within limitation.

¶ 7 · ¶ 8 (quoting WP 590/2026 · ¶ 33)

03Law Applied

The Court relied on Article 136 of the Limitation Act, 1963, under which limitation for execution of a decree runs from when it "becomes enforceable".

¶ 5 (quoting WP 590/2026 · ¶ 28)

It applied Section 36 of the Arbitration Act, 1996, in both its original and amended forms, and Section 26 of the 2015 Amendment Act, as construed in Board of Control for Cricket in India v. Kochi Cricket Pvt. Ltd. (2018) 6 SCC 287, which made amended Section 36 applicable to court proceedings pending on or after 23.10.2015.

¶ 5 (quoting WP 590/2026 · ¶ 17–18, 23)

It relied on National Aluminium Co. v. Pressteel & Fabrications (2004) 1 SCC 540, and the decisions following it, which held that filing a Section 34 application automatically stayed enforcement, as the binding law until 2015.

¶ 5 (quoting WP 590/2026 · ¶ 13, 27)

It applied Hindustan Construction Co. Ltd. v. Union of India (2020) 17 SCC 324, which held that the automatic-stay reading was per incuriam, struck down Section 87 of the 2019 Amendment, and confirmed that amended Section 36 applies to proceedings instituted after 23.10.2015.

¶ 5 (quoting WP 590/2026 · ¶ 21–23)

It drew on Deep Chand v. Mohan Lal (2000) 6 SCC 259, Hameed Joharan v. Abdul Salam (2001) 7 SCC 573, and Akkayanaicker v. A.A.A. Kotchadainaidu (2004) 12 SCC 469, holding that limitation runs only from the date the decree-holder acquires the legal right and practical ability to enforce.

¶ 5 (quoting WP 590/2026 · ¶ 28)

It also applied the maxim lex non cogit ad impossibilia and, by analogy, Section 15(1) of the Limitation Act, 1963.

¶ 5 (quoting WP 590/2026 · ¶ 28–29)

Provisions in the judgment · 12 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 9 provisionsSection 9Section 21Section 31Section 34Section 35Section 36Section 37Section 43Section 87

India International Arbitration Centre Act, 2019 Section 15

Limitation Act, 1963 Section 136Section 15

04Reasoning

The Court adopted the reasoning of WP 590/2026 because the facts and legal issue were identical.

¶ 7

Under the unamended Section 36, as then binding through NALCO, enforcement of the award was barred while the Section 34 challenge was pending. The award-holder therefore had no effective remedy of execution until the bar lifted on 23.10.2015.

¶ 5 (quoting WP 590/2026 · ¶ 27–28)

The Court held that the period before 23.10.2015 could not be counted toward limitation, relying on the principle that limitation cannot run when enforcement is legally unavailable.

¶ 5 (quoting WP 590/2026 · ¶ 28–29, 32)

The petitioners' reliance on Hindustan Construction was rejected because that judgment corrected the legal position without retrospectively altering the remedy available during the intervening period.

¶ 5 (quoting WP 590/2026 · ¶ 27)

The Court also reasoned that counting the pendency period against the award-holder would let a pending challenge defeat an award without any default on its part, which is inconsistent with the 2015 amendment's object.

¶ 5 (quoting WP 590/2026 · ¶ 30–31)

Applying this, limitation began on 23.10.2015 and expires on 23.10.2027, so the execution filed on 16.09.2025 is within time.

¶ 5 (quoting WP 590/2026 · ¶ 33)

The Commercial Court's exclusion of the 25.02.2011–23.10.2015 period is consistent with this approach.

¶ 5

The order does not expressly address the petitioners' 24.02.2023 computation or the effect of the pendency of the Section 37 appeal from 2017 to 2025.

¶ 3, 5–8

05Holding

The Court holds that the period for executing the award runs from 23.10.2015, when amended Section 36 became operative, and not from the date of the award, because enforcement was legally barred during the pendency of the Section 34 proceedings under the then-binding NALCO line of authority.

¶ 5 (quoting WP 590/2026 · ¶ 33)

The execution application filed on 16.09.2025 is therefore within limitation under Article 136, and the objection is rejected.

¶ 7–8

The writ petition under Article 227 is dismissed, and the Commercial Court's order dated 08.09.2026 in Execution Case No. 30/2025 is upheld.

¶ 8
Chhattisgarh High Court

Original Court PDF

SOUTH EASTERN COALFIELDS LIMITEDvsM/S SHYAM LAL AGRAWAL CONTRACTOR

Chhattisgarh High Court · November 27, 2026