National Company Law Appellate TribunalInsolvency and Bankruptcy LawCivil Procedure and Evidence

Limitation for IBC appeals runs from pronouncement; delay beyond the fifteen-day statutory limit is not condonable.

Harish Shahv.Ramakrishnan Sadasivan Resolution Professional Of M/S. Lokaa Developer Pvt Ltd

Limitation for IBC appeals runs from pronouncement; delay beyond the fifteen-day statutory limit is not condonable.. Harish Shah vs Ramakrishnan Sadasivan Resolution Professional Of M/S. Lokaa Developer Pvt Ltd. National Company Law Appellate Tribunal. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the limitation period for filing an appeal under Section 61 of the IBC commences from the date of pronouncement of the order or the date of uploading/knowledge of the order.

The court held

The Tribunal held that the appeals were barred by limitation as they were preferred on the 46th day from the date of pronouncement.

It also directed

The court answered that limitation under Section 61(2) of the IBC commences from the date of pronouncement in open court and not from the date of uploading.

Consequently, IA Nos. 135 & 142/2026 (for condonation of delay) were rejected, and Company Appeals (AT) (CH) (INS) Nos. 54 & 56 / 2026 were dismissed as barred by limitation.

01Facts

The Appellants, acting as unsecured financial creditors and homebuyers of the Corporate Debtor (M/s. Lokaa Developer Pvt. Ltd.), challenged an order dated 28.10.2025 passed by the Adjudicating Authority (NCLT).

p. 3

The impugned order approved a Resolution Plan submitted by the "Mone Flat Owners Association" under Section 30(6) of the Insolvency and Bankruptcy Code (IBC).

¶ 3

The Appellants filed their appeals electronically on 13.12.2025.

¶ 4

They contended that the limitation period should be calculated from 30.10.2025, the date the order was uploaded on the NCLT e-portal, rather than the date of pronouncement.

¶ 5

The Registry reported a delay of 16 days, while the Appellants sought condonation for 14 days, asserting the delay was due to time taken to obtain the order and seek legal advice.

¶ 4-5

Notably, the Appellants did not apply for a certified copy of the order and instead sought an exemption from filing it.

¶ 10-11

02Issues

i.1. Whether the limitation period for filing an appeal under Section 61 of the IBC commences from the date of pronouncement of the order or the date of uploading/knowledge of the order.

¶ 7, 16

ii.2. Whether the Appellate Tribunal has the statutory authority to condone a delay that exceeds the 15-day period prescribed under the proviso to Section 61(2) of the IBC.

¶ 12, 18

03Law Applied

The court primarily applied Section 61(2) of the IBC, which mandates that appeals must be filed within 30 days, with a proviso allowing a maximum extension of only 15 days upon showing sufficient cause.

¶ 12

It relied on the Supreme Court precedent in V. Nagarajan v. SKS Ispat and Power Limited, which clarifies that the IBC framework does not link limitation to the receipt of a certified copy, but rather to the date of pronouncement.

¶ 13

The court further cited A. Rajendra v. Gonugunta Madhusudhan Rao and Ashdan Properties Pvt. Ltd. v. DSK Global Education and Research Pvt. Ltd., affirming that limitation starts from the date of pronouncement in open court, and relief under Section 12(2) of the Limitation Act (excluding time for preparing a certified copy) is only available if an application for a certified copy was made within the initial limitation period.

¶ 13, 16

Provisions in the judgment · 5 · Linked ones open on LawLens

Insolvency and Bankruptcy Code, 2016. Section 30Section 60Section 61

Limitation Act, 1963 Section 12

Companies Act, 2013 Section 421

04Reasoning

The Tribunal determined that since the order was pronounced on 28.10.2025, the 30-day limitation period ended on 27.11.2025.

¶ 7, 9

Including the maximum condonable period of 15 days, the absolute deadline to file the appeal was 12.12.2025.

¶ 9

The Appellants filed the appeal on 13.12.2025, which was the 46th day.

¶ 18

The Tribunal rejected the plea to calculate limitation from the date of uploading (30.10.2025), noting that as members of the Committee of Creditors (CoC), the Appellants were deemed to have knowledge of the proceedings and the pronouncement.

¶ 6, 14

Furthermore, because the Appellants failed to even apply for a certified copy, they were ineligible for any time exclusion under the Limitation Act.

¶ 11, 13

The Tribunal emphasized that Section 61(2) is a self-contained provision with a strict "upper limit" of 45 days, leaving the court with no jurisdiction to condone a delay of even a single day beyond that threshold.

¶ 12, 18

05Holding

The Tribunal held that the appeals were barred by limitation as they were preferred on the 46th day from the date of pronouncement.

¶ 18

The court answered that limitation under Section 61(2) of the IBC commences from the date of pronouncement in open court and not from the date of uploading.

¶ 17

Consequently, IA Nos. 135 & 142/2026 (for condonation of delay) were rejected, and Company Appeals (AT) (CH) (INS) Nos. 54 & 56 / 2026 were dismissed as barred by limitation.

¶ 18
National Company Law Appellate Tribunal

Original Court PDF

Harish ShahvsRamakrishnan Sadasivan Resolution Professional Of M/S. Lokaa Developer Pvt Ltd

National Company Law Appellate Tribunal · April 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment