01Facts
The Appellant (Contractor) filed a claim for Rs. 84,04,943/- against the Respondent for work completed on 20.08.2015.
p. 2The Appellant raised final invoices on 22.08.2015.
p. 2During arbitration, the Respondent admitted a liability of only Rs. 16,75,128/- (a 5% retention amount) via email dated 19.07.2018.
¶ 14, 16The Appellant filed an application under Order XII Rule 6 CPC for a judgment on this admission, while the Respondent filed an application under Order VII Rule 11 CPC to dismiss the remainder of the claim as time-barred.
p. 5The Arbitrator issued an interim award allowing the claim for the admitted amount but dismissing the balance.
p. 6The Appellant challenged this under Section 34 of the Arbitration and Conciliation Act, 1996, which the District Judge dismissed on 15.09.2025.
pp. 1-202Issues
i.1. Whether the claim for the amount exceeding Rs. 16,75,128/- was barred by limitation under the Limitation Act, 1963.
p. 8 / para. 12ii.2. Whether the question of limitation in this specific context constituted a mixed question of law and fact that precluded dismissal under Order VII Rule 11 CPC.
p. 9 / para. 1503Law Applied
Article 18 of the Schedule to the Limitation Act, 1963, which stipulates a three-year limitation period for suits for the price of work done where no time for payment is fixed, commencing from the date the work is completed.
p. 10Section 18 of the Limitation Act, 1963, regarding the effect of acknowledgment in writing, which requires an unequivocal and express admission of liability before the expiration of the limitation period to start a fresh period.
¶ 12, 13Order VII Rule 11 CPC concerning the rejection of a claim when it is "barred by any law" based on the statements in the claim itself.
p. 2, 11Provisions in the judgment · 6 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 37
Code of Civil Procedure, 1908 Section 7Section 12
Limitation Act, 1963 Section 18Section 1
04Reasoning
The Court observed that the work was completed on 22.08.2015, meaning the limitation period expired on 19.08.2018. Since the arbitration was invoked on 10.09.2018—beyond the three-year window—the claim was prima facie barred.
p. 10The Court analyzed the correspondence and found that while the Respondent's email dated 19.07.2018 constituted a valid acknowledgment under Section 18, it was strictly limited to the specific sum of Rs. 16,75,128/-.
¶ 15, 20The Court held that where the facts (completion date and invoice dates) are admitted by the claimant in their own pleadings and documents, and these facts conclusively prove the claim is time-barred, the court/tribunal can decide the issue as a matter of law under Order VII Rule 11.
¶ 22, 2305Holding
The Court held that the claim over and above the acknowledged amount of Rs. 16,75,128/- was clearly barred by limitation as per Article 18, and no acknowledgment existed under Section 18 to extend the limitation for the balance.
¶ 20, 23The High Court dismissed the appeal and upheld the findings of the learned Arbitrator and the District Judge, affirming that when a claim is found to be time-barred on the face of the averments in the Statement of Claim, it is liable for rejection.
¶ 23, 27Original Court PDF
M/S Quality Engineers And Contractors & Anr.vsM/S Distribution Logistics Infrastructure Private Ltd & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
