Kerala High CourtArbitration and MediationContract Law

Liquidated damages under Section 74 require proof of actual loss; Section 37 review cannot reappreciate arbitral merits.

BHARAT SANCHAR NIGAM LIMITEDv.RAMACHANDRA PAI (DIED)

Liquidated damages under Section 74 require proof of actual loss; Section 37 review cannot reappreciate arbitral merits.. BHARAT SANCHAR NIGAM LIMITED vs RAMACHANDRA PAI (DIED). Kerala High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the District Court's rejection of BSNL's claim for liquidated damages, on the ground that no loss or injury was proved, is correct and sustainable under Section 37 of the Arbitration and Conciliation Act, 1996.

The court held

The Court answered the sole issue in the affirmative: the rejection of BSNL's claim for liquidated damages was correct, as BSNL failed to prove actual loss and the District Court's finding was not vitiated by any error warranting interference under Section 37.

It also directed

The appeal was held to be meritless and is dismissed.

The District Court's order dated 03.06.2016 in O.P. (Arb) No. 312 of 2013, insofar as it rejected BSNL's claim on Point No. 4, stands affirmed.

01Facts

The 1st respondent (since deceased) entered into an agreement with BSNL (appellant) for marketing and distribution of BSNL services for three years from 11.06.2010, and furnished a performance bank guarantee (PBG) of Rs. 3,00,000.

p. 3 · ¶ 1(i)

When BSNL decided to deduct income tax from the commission payable, the respondent invoked clause 7.2 and sought withdrawal from the agreement. BSNL accepted the resignation but did not return the PBG.

pp. 3–4 · ¶ 1(ii)–(iii)

At the respondent's request, BSNL appointed its Divisional Engineer as sole arbitrator. The arbitrator rejected the respondent's claim.

p. 4 · ¶ 1(iv)–(v)

The respondent challenged the award under Section 34 before the District Court, Thalassery (O.P. (Arb) No. 312 of 2013). During the pendency, the respondent died and his legal representatives were impleaded.

p. 4 · ¶ 1(vi)–(vii)

The District Court framed six points and upheld the award on all points except Point No. 4, which concerned BSNL's claim for liquidated damages. The District Court held that the court may award only reasonable compensation not exceeding the contractual amount, that no compensation is payable where no loss is proved, and that BSNL suffered no legal injury.

p. 5 · ¶ 1(viii) · ¶ 4–5

BSNL appealed under Section 37 against the Point No. 4 finding.

p. 5 · ¶ 1(ix)

02Issues

i.1. Whether the District Court's rejection of BSNL's claim for liquidated damages, on the ground that no loss or injury was proved, is correct and sustainable under Section 37 of the Arbitration and Conciliation Act, 1996.

p. 5 · ¶ 3

03Law Applied

Under Section 74 of the Indian Contract Act, 1872, the court must not enforce a penalty but may award only reasonable compensation not exceeding the stipulated sum, as explained in Fateh Chand v. Balkishan Das, AIR 1963 SC 1405.

p. 5 · ¶ 4

BSNL v. Reliance Communications Ltd., (2011) 1 SCC 394 applied the same principle to telecom contracts.

p. 5 · ¶ 4

State of Kerala v. United Shippers & Dredgers, 1982 KLT 738 holds that where no loss results from breach, no compensation is payable.

pp. 5–6 · ¶ 4

Under Section 37, appellate review is confined within the limits of Section 34. An appellate court cannot re-appreciate the merits of an arbitral award or substitute a different view, as held in MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163 and Konkan Railway Corporation Ltd. v. Chenab Bridge Project Undertaking, (2023) 9 SCC 85.

p. 6 · ¶ 6 · pp. 6–7 · ¶ 7

Interference is warranted only for patent illegality, perversity, or conduct shocking the conscience.

p. 8 · ¶ 9

Provisions in the judgment · 3 · Linked ones open on LawLens

Indian Contract Act, 1872 Section 74

Arbitration and Conciliation Act, 1996 Section 34Section 37

04Reasoning

The Court first noted the District Court's reasoning: under Section 74 the claimant must prove loss, and absent proof of loss the party in breach is not entitled to any compensation. Applying the limited Section 37 standard from MMTC and Konkan Railway, the Court declined to re-examine the factual finding on loss.

p. 5 · ¶ 4–5 · pp. 6–7 · ¶ 6–8

It then found on the record that BSNL had "miserably failed" to prove actual damages caused by the respondent's termination of the franchise, and that no material was produced to establish such damages. On that basis, the Court held that the District Court's finding was not erroneous, illegal, or perverse, and did not shock the conscience.

pp. 7–8 · ¶ 9

The judgment does not independently analyse Section 74 or the enforceability of the PBG forfeiture; it rests its conclusion on the failure of proof of loss and the deferential scope of Section 37 review.

pp. 7–8 · ¶ 8–9

05Holding

The Court answered the sole issue in the affirmative: the rejection of BSNL's claim for liquidated damages was correct, as BSNL failed to prove actual loss and the District Court's finding was not vitiated by any error warranting interference under Section 37.

p. 8 · ¶ 9

The appeal was held to be meritless and is dismissed.

p. 8 · ¶ 9

The District Court's order dated 03.06.2016 in O.P. (Arb) No. 312 of 2013, insofar as it rejected BSNL's claim on Point No. 4, stands affirmed.

p. 8 · ¶ 9
Kerala High Court

Original Court PDF

BHARAT SANCHAR NIGAM LIMITEDvsRAMACHANDRA PAI (DIED)

Kerala High Court · November 24, 2026