In brief

The question

1. Whether the respondents should be directed to take enforcement action to remove the identified road encroachments.

The court held

The Court directed respondents 2 and 3 to complete the enforcement action and removal of the encroachments within twelve weeks from receipt of a copy of the order.

It also directed

The writ petition was disposed of without costs, and any connected miscellaneous petitions were closed.

01Facts

The petitioner sought a writ of mandamus directing the respondents, particularly the Tahsildar, to remove alleged encroachments on both sides of the road from Sigar Village Bridge to Mudikandoor, a distance of 1.4 km, relying on a representation dated 30 April 2023.

p. 1

The State submitted that revenue authorities had surveyed the area, identified encroachments, and issued a Form I notice to the Block Development Officer, who was to take enforcement action under the applicable procedures.

p. 2

02Issues

i.1. Whether the respondents should be directed to take enforcement action to remove the identified road encroachments.

pp. 1–2

ii.2. Whether that action should be completed within a time fixed by the Court.

pp. 1–2

03Law Applied

The petition invoked the High Court’s jurisdiction under Article 226 of the Constitution of India to seek a writ of mandamus.

p. 1

The Court directed removal of the encroachments in accordance with the procedures contemplated by the relevant statutes and rules; it did not identify any particular enactment, statutory provision, or precedent.

p. 2

04Reasoning

The Court relied on the State’s submission, supported by the Tahsildar’s written instructions, that a survey had identified encroachments and that a Form I notice had been issued to the Block Development Officer.

p. 2

In light of that progress, the Court directed respondents 2 and 3 to proceed with enforcement and remove the encroachments, subject to the procedures under the applicable statutes and rules.

p. 2

05Holding

The Court directed respondents 2 and 3 to complete the enforcement action and removal of the encroachments within twelve weeks from receipt of a copy of the order.

p. 2

The writ petition was disposed of without costs, and any connected miscellaneous petitions were closed.

p. 3
Madras High Court

Original Court PDF

P.SenthilvsThe District collector

Madras High Court · November 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment