01Facts
The petitioner operated a 1 MW rooftop solar plant at its manufacturing unit for captive consumption. It contended that the plant was on the internal load side, protected against reverse power flow, and neither injected energy into nor received credits from the grid.
p. 3On 28 September 2026, the respondents inspected the premises and sealed the Air Circuit Breaker’s spring-charging handle, stopping the plant.
p. 4The petitioner’s representations seeking removal of the seal were followed by a show-cause notice demanding parallel-operation/network charges, later revised to Rs.94,88,539.
p. 4The petitioner sought a direction to remove the seal and permit the plant to operate.
p. 1, 502Issues
i.1. Whether the respondents could seal the petitioner’s solar plant without prior notice or hearing
pp. 5, 7–8ii.2. Whether the petitioner required prior approval, or only prior intimation, to operate the solar plant for captive consumption
pp. 6–803Law Applied
The Court referred to the Tamil Nadu Electricity Regulatory Commission regulations framed under Sections 61(h), 86(1)(e) and 181 of the Electricity Act, 2003.
p. 6Regulation 8.14 provides that a grid-connected renewable energy generating system behind the consumer’s meter, where the consumer has not opted for net metering or net billing, may be allowed upon prior intimation to the distribution licensee.
p. 6Regulation 8.5 permits disconnection where a grid-interactive solar PV system is found operating in parallel with the distribution licensee’s supply system without approval, subject to three days’ notice; restoration follows isolation of the plant from the licensee’s supply system.
p. 7The Court also applied the principles of natural justice, requiring notice and an opportunity to be heard before the impugned action.
p. 8Provisions in the judgment · 3 · Linked ones open on LawLens
Electricity Act, 2003 Section 61Section 86Section 181
04Reasoning
The Court read Regulations 8.14 and 8.5 as distinguishing a plant operating behind the consumer’s meter for personal consumption from an unauthorised plant running in parallel with the distribution system.
pp. 6–8It understood the regulations to require prior intimation, rather than prior approval, for the former.
p. 8The Board had not given the petitioner notice or a hearing before sealing the plant, and it was already aware of the plant’s existence; the Court also noted that a similar sealing in 2021 had been reversed and operation permitted.
p. 8In those circumstances, the sealing was contrary to natural justice, while the alleged connection to the grid could be examined through a subsequent joint inspection.
pp. 7–805Holding
The Court allowed the writ petition in part by directing the respondents to remove the seal and restore the connection forthwith, and to conduct a joint inspection within two weeks of receiving a copy of the order.
p. 8The writ petition was disposed of with no order as to costs, and the connected miscellaneous petition was closed.
p. 8Original Court PDF