Madras HC Sets Aside ₹5 Lakh Award, Says RERA Allottee Who Doesn’t Withdraw From Delayed Project Can Claim Interest, Not Compensation

SPR Constructions Private Limited vs Silambuselvi K

Madras High CourtJUDGMENT: October 16, 20263 MIN READSOURCE JUDGMENT
Madras HC Sets Aside ₹5 Lakh Award, Says RERA Allottee Who Doesn’t Withdraw From Delayed Project Can Claim Interest, Not Compensation. SPR Constructions Private Limited vs Silambuselvi K. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The allottee entered into sale and construction agreements with the promoter in August 2019 for a commercial unit in the “Market of India” project.

Source reference: pp. 2–6

She paid approximately 90% of the consideration.

Source reference: pp. 2–6

Although possession was due by June 2022, with a six-month grace period, the promoter failed to complete construction and hand over the unit.

Source reference: pp. 2–6

The allottee complained under Sections 31 and 71 of the Real Estate (Regulation and Development) Act, 2016 (“RERA”), seeking compensation for mental agony and costs.

Source reference: pp. 2–6

The Adjudicating Officer awarded ₹5,00,000 as compensation and ₹50,000 as costs.

Source reference: pp. 2–6

The promoter challenged that order under Article 227, contending that the allottee, who had not withdrawn from the project, could claim interest for delay but not compensation under Section 18(1).

Source reference: pp. 2–6

The allottee objected that the revision was not maintainable because RERA provided an appeal remedy.

Source reference: pp. 7–8
02

Issues

Whether the High Court could entertain a petition under Article 227 despite the statutory appeal remedy under RERA, where the challenge alleged that the Adjudicating Officer had acted beyond its jurisdiction.

Source reference: pp. 8–10

Whether an allottee who does not withdraw from the project may receive compensation under Section 18(1), in addition to interest for the delay in handing over possession.

Source reference: pp. 10–13, 16–17
03

Law Applied

Section 18(1) of RERA provides for return of the amount paid, interest and compensation where an allottee withdraws from a project because the promoter has failed to deliver possession; its proviso provides an allottee who does not withdraw with interest for each month of delay until possession is handed over.

Source reference: pp. 10–12

The Court read Sections 12, 14 and 19 as addressing distinct grounds for compensation, including false statements, specified defects or obligations, and certain failures involving discontinuance of the developer’s business; it found those provisions inapplicable to the claim before it.

Source reference: pp. 14–17

Section 71 confers on the Adjudicating Officer authority to determine compensation claims under Sections 12, 14, 18 and 19, but does not independently expand the circumstances in which compensation is payable.

Source reference: p. 17

The Court also referred to the statutory appeal under Section 33 and the principles in Geeta Bai v. K. Arjun Singh and Nandi Infrastructure Corridor Enterprises Ltd. v. B. Gurappa Naidu concerning Article 227 review for jurisdictional error or patent error of law.

Source reference: pp. 8–9, 13
04

Reasoning

The promoter admitted that possession had not been delivered by the agreed date, but the allottee remained willing to continue with the project.

Source reference: pp. 11–17

The Court therefore treated the case as falling under the proviso to Section 18(1), which, in its view, entitled the allottee to delay interest but not compensation.

Source reference: pp. 11–17

It rejected reliance on Sections 12, 14 and 19 because the claim did not concern false advertising, defects covered by Section 14, or discontinuance of the developer’s business.

Source reference: pp. 11–17

Since Section 71 did not create a separate entitlement to compensation, the Adjudicating Officer had exceeded its statutory authority by awarding compensation.

Source reference: pp. 11–17

The Court considered that jurisdictional error sufficient to entertain the Article 227 petition despite the available appeal remedy.

Source reference: pp. 11–17
05

Holding

The High Court held that the revision was maintainable under Article 227 and that an allottee who continued with the project was entitled, in the circumstances of this case, to interest for each month of delay but not compensation under Section 18(1).

It allowed the revision, set aside the compensation award of ₹5,00,000 and the related costs award of ₹50,000, and left the parties to pursue their respective positions on delay interest in the pending proceeding.

Source reference: pp. 12–13, 17–18

No costs were ordered in the revision.

Source reference: pp. 12–13, 17–18
06

Acts & Sections Cited

8 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Madras High Court

Original Court PDF

SPR Constructions Private LimitedvsSilambuselvi K

Madras High Court · October 16, 2026