Facts
The allottee entered into sale and construction agreements with the promoter in August 2019 for a commercial unit in the “Market of India” project.
Source reference: pp. 2–6She paid approximately 90% of the consideration.
Source reference: pp. 2–6Although possession was due by June 2022, with a six-month grace period, the promoter failed to complete construction and hand over the unit.
Source reference: pp. 2–6The allottee complained under Sections 31 and 71 of the Real Estate (Regulation and Development) Act, 2016 (“RERA”), seeking compensation for mental agony and costs.
Source reference: pp. 2–6The Adjudicating Officer awarded ₹5,00,000 as compensation and ₹50,000 as costs.
Source reference: pp. 2–6The promoter challenged that order under Article 227, contending that the allottee, who had not withdrawn from the project, could claim interest for delay but not compensation under Section 18(1).
Source reference: pp. 2–6The allottee objected that the revision was not maintainable because RERA provided an appeal remedy.
Source reference: pp. 7–8Issues
Whether the High Court could entertain a petition under Article 227 despite the statutory appeal remedy under RERA, where the challenge alleged that the Adjudicating Officer had acted beyond its jurisdiction.
Source reference: pp. 8–10Whether an allottee who does not withdraw from the project may receive compensation under Section 18(1), in addition to interest for the delay in handing over possession.
Source reference: pp. 10–13, 16–17Law Applied
Section 18(1) of RERA provides for return of the amount paid, interest and compensation where an allottee withdraws from a project because the promoter has failed to deliver possession; its proviso provides an allottee who does not withdraw with interest for each month of delay until possession is handed over.
Source reference: pp. 10–12The Court read Sections 12, 14 and 19 as addressing distinct grounds for compensation, including false statements, specified defects or obligations, and certain failures involving discontinuance of the developer’s business; it found those provisions inapplicable to the claim before it.
Source reference: pp. 14–17Section 71 confers on the Adjudicating Officer authority to determine compensation claims under Sections 12, 14, 18 and 19, but does not independently expand the circumstances in which compensation is payable.
Source reference: p. 17The Court also referred to the statutory appeal under Section 33 and the principles in Geeta Bai v. K. Arjun Singh and Nandi Infrastructure Corridor Enterprises Ltd. v. B. Gurappa Naidu concerning Article 227 review for jurisdictional error or patent error of law.
Source reference: pp. 8–9, 13Reasoning
The promoter admitted that possession had not been delivered by the agreed date, but the allottee remained willing to continue with the project.
Source reference: pp. 11–17The Court therefore treated the case as falling under the proviso to Section 18(1), which, in its view, entitled the allottee to delay interest but not compensation.
Source reference: pp. 11–17It rejected reliance on Sections 12, 14 and 19 because the claim did not concern false advertising, defects covered by Section 14, or discontinuance of the developer’s business.
Source reference: pp. 11–17Since Section 71 did not create a separate entitlement to compensation, the Adjudicating Officer had exceeded its statutory authority by awarding compensation.
Source reference: pp. 11–17The Court considered that jurisdictional error sufficient to entertain the Article 227 petition despite the available appeal remedy.
Source reference: pp. 11–17Holding
The High Court held that the revision was maintainable under Article 227 and that an allottee who continued with the project was entitled, in the circumstances of this case, to interest for each month of delay but not compensation under Section 18(1).
It allowed the revision, set aside the compensation award of ₹5,00,000 and the related costs award of ₹50,000, and left the parties to pursue their respective positions on delay interest in the pending proceeding.
Source reference: pp. 12–13, 17–18No costs were ordered in the revision.
Source reference: pp. 12–13, 17–18Acts & Sections Cited
8 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Real Estate (Regulation and Development) Act, 2016.8
Original Court PDF
SPR Constructions Private LimitedvsSilambuselvi K
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
