01Facts
The 22 petitioners, residents of K. Kodihalli, Agoralinganadoddi, Hunasemaradadoddi and other villages in Maddur Taluk, Mandya District, had their lands acquired for the construction of National Highway-275 across the Shimsha river.
¶ 2The petitioners accepted the acquisition on the understanding that a service or connecting road would be built across the river linking K. Kodihalli to Maddur.
¶ 2The petitioners later learned that no such link road was planned, and K. Kodihalli lies about 300 metres from the Shimsha bridge.
¶ 2By representation dated 01.02.2020 (Annexure-D), the petitioners requested the respondents (Union of India, NHAI and its Project Director) to construct a 20-ft bridge to serve school children, the elderly, the handicapped and other villagers.
¶ 2The petitioners sought a writ of mandamus directing action on that representation.
¶ 1The petitioners later applied to amend the petition to add prayers on rectification of the NHAI design by constructing lane-over bridges at three points.
¶ 4NHAI stated that a two-lane service road already exists at the major Shimsha river bridge on the Bengaluru–Mysuru expressway, and that lane-over bridges at the points listed in the respondent's memo are under construction.
¶ 502Issues
i.1. Whether the petitioners' principal grievance, namely the absence of a connecting road/bridge across the Shimsha river, stands redressed in light of the service road already provided and the lane-over bridges under construction.
¶ 5 · ¶ 6ii.2. Whether any residual grievance of the petitioners should be left for determination by NHAI in the first instance, rather than being adjudicated in these writ proceedings.
¶ 703Law Applied
The petition was filed under Article 226 of the Constitution of India seeking a writ of mandamus to compel the respondents to act on a representation.
¶ 1Where the substantive grievance has been redressed by the authority's action, no mandamus is required, and any remaining grievance is to be pursued before the competent authority, which must examine it in accordance with law.
¶ 6 · ¶ 704Reasoning
The Court heard both sides and considered the amendment application.
¶ 3 · ¶ 4The Court accepted NHAI's statement that a two-lane service road already serves the major Shimsha bridge and that lane-over bridges are under construction at the identified points.
¶ 5On that basis, the Court held that the petitioners' main grievance stood redressed.
¶ 6Because the core relief sought had been met by the respondents' own actions, the Court found no need to compel further action through mandamus.
¶ 6For any further grievance, the Court left the petitioners free to represent it to NHAI, which was directed to examine the matter and take appropriate steps in accordance with law.
¶ 7The judgment does not record any finding on whether a connecting bridge across the Shimsha river was legally required, nor does it expressly decide the amendment application.
05Holding
The Court held that the petitioners' main grievance has been redressed by the service road and the lane-over bridges already provided or under construction.
¶ 6The petitioners were given liberty to raise any further grievance before NHAI, which "shall look into the matter and take appropriate steps in accordance with law."
¶ 7The writ petition was disposed of accordingly. No mandamus or other substantive direction was issued beyond this direction to NHAI.
¶ 8Original Court PDF
SRI C CHELUVARAJUvsTHE UNION OF INDIA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in