Facts
The respondent (plaintiff) filed O.S. No. 64 of 2013 seeking a declaration of ownership of 'B' schedule property, a permanent injunction, and a mandatory injunction to remove the appellant's (defendant's) construction on said property
Source reference: p.3Earlier, the respondent had filed O.S. No. 266 of 2011 for a declaration of ownership of a pathway, while the appellant filed O.S. No. 114 of 2011 for a permanent injunction
Source reference: p.4The Trial Court in O.S. No. 64 of 2013 granted the declaration but refused the mandatory injunction, finding the construction existed since 1985
Source reference: p.3, 5However, the First Appellate Court (A.S. No. 123 of 2014) reversed this, granting the mandatory injunction on the grounds that the respondent only discovered the encroachment via the Advocate Commissioner’s report
Source reference: p.3, 4The appellant challenged these findings in the Second Appeals
Source reference: p.1-2Issues
1. Whether the First Appellate Court was correct in holding that the respondent learned of the encroachment only through the Advocate Commissioner’s report and not in 1985, thereby granting the relief of mandatory injunction beyond the statutory period of limitation?
Source reference: p.4-5 / para. 62. Whether the concurrent findings regarding the easementary nature of the suit pathway in O.S. No. 114 of 2011 and O.S. No. 266 of 2011 warrant interference under Section 100 of the CPC?
Source reference: p.7 / para. 11Law Applied
The Court applied Section 100 of the Civil Procedure Code (CPC), which limits High Court intervention in second appeals to cases involving substantial questions of law and prohibits interference with concurrent findings of fact unless they are perverse
Source reference: p.6, 8The Court applied the principles of the Law of Limitation regarding mandatory injunctions and the doctrine of "Easement of Necessity," emphasizing that such a right should be restricted to the minimum extent required for ingress and egress and cannot be claimed as a "luxury"
Source reference: p.5-6 / para. 8Reasoning
The High Court found that the respondent had explicitly admitted during trial that the appellant's construction on the suit pathway was put up as early as 1985
Source reference: p.6 / para. 9, 11Consequently, the Court held that the First Appellate Court’s finding—that the respondent only realized there was an encroachment after the Advocate Commissioner’s report—was a "clear perversity" and a failure to appreciate the evidence on record
Source reference: p.7 / para. 11Since the encroachment was known since 1985, the prayer for a mandatory injunction in 2013 was "hopelessly time barred"
Source reference: p.6 / para. 9Regarding the easementary rights, the Court noted that while the respondent established a right of access, they were already enjoying access despite the construction; therefore, equity did not favor a mandatory injunction for a delayed claim
Source reference: p.6 / para. 8Holding
The High Court answered the substantial question of law in favor of the appellant
It partly allowed S.A.(MD) No. 594 of 2021, setting aside the First Appellate Court's decree for a mandatory injunction and restoring the Trial Court's judgment, which granted only the declaratory relief
Source reference: p.8 / para. 12S.A.(MD) Nos. 97 and 98 of 2022 were dismissed, as the concurrent findings of the lower courts in those suits did not present any substantial question of law
Source reference: p.8 / para. 12No costs were ordered
Source reference: p.8Original Court PDF
V.M.THANGADURAIvsL.RAJAGOPAL
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in