Facts
The Appellants (Rajasthan Discoms) challenged an order of the Central Electricity Regulatory Commission (CERC) dated 25.09.2019, which granted "Change in Law" compensation to Respondent No. 2 (Maruti Clean Coal and Power Limited)
Source reference: p. 4, para. 1The dispute arose from a Power Purchase Agreement (PPA) executed on 01.11.2013 with a bid cut-off date of 11.09.2012
Source reference: p. 4, para. 7While several claims were initially raised, the appeal was narrowed down to a single issue: whether the levy of "Forest Tax" (Forest Transit Fee) in Chhattisgarh constituted a "Change in Law."
Source reference: no citationThe Appellants argued that since a 2002 Notification already existed prior to the cut-off date, the Respondent was only entitled to the incremental increase (from ₹7 to ₹15), rather than the full amount
Source reference: p. 7, para. 12Issues
1. Whether the mere existence of a 2002 Notification regarding Forest Tax, without active enforcement/recovery prior to the cut-off date, precludes a "Change in Law" claim
Source reference: p. 9, para. 162. Whether the "Forest Tax" made mandatorily applicable via administrative directions after the cut-off date entitles the generator to full restitutionary compensation
Source reference: p. 13, para. 21Law Applied
The Tribunal applied Article 10.1.1 of the PPA, which defines "Change in Law" as the enactment, coming into effect, application, or interpretation of Law resulting in additional expenditure
Source reference: p. 14, para. 26It relied on the Supreme Court’s decision in Energy Watchdog v. CERC (2017), which established that Change in Law provisions are "restitutionary" in nature, intended to restore the affected party to the same economic position
Source reference: p. 16, para. 30It further applied GMR Warora Energy Limited v. CERC (2023) and Adani Power Limited v. RERC (2018), which held that additional charges payable due to notifications or directions issued by State instrumentalities after the cut-off date qualify as Change in Law events
Source reference: p. 15, para. 27; p. 19, para. 37Reasoning
The Tribunal rejected the Appellants' reliance on the 2002 Notification because it was not pleaded before the CERC and was introduced only during final arguments
Source reference: p. 13, para. 24On merits, the Tribunal found that although the 2002 Notification existed, the Forest Department’s letter dated 31.10.2012 proved that the transit fee was made mandatorily applicable only from 01.11.2012—which was after the 11.09.2012 cut-off date
Source reference: p. 17-18, para. 34-35The Tribunal reasoned that under Article 10.1.1, the "coming into effect" or "application" of a law is distinct from its "enactment."
Source reference: p. 16, para. 31Since the levy was dormant and not operationally recovered at the time of the bid, a prudent bidder could not have factored it into the tariff
Source reference: p. 16, para. 30; p. 19, para. 36The Tribunal noted the Appellants failed to provide evidence of any recovery of this tax from any generator prior to the mandatory start date of 01.11.2012
Source reference: p. 19, para. 36Holding
The Tribunal upheld the CERC’s order, holding that the Respondent is entitled to Change in Law compensation for the full Forest Tax amount (₹7/MT from 01.11.2012 to 30.06.2015, and ₹15/MT from 01.07.2015 onwards)
The Tribunal concluded there was no error in the Impugned Order as the tax became operationally effective only after the cut-off date. The appeal and all pending applications were dismissed
Source reference: p. 21, para. 41; p. 21Original Court PDF
RAJASTHAN URJA VIKAS NIGAM LTD & Ors.vsCENTRAL ELECTRICITY REGULATORY COMMISSION & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in