Facts
The Appellant, a registered contractor, participated in a tender process (NIB No. 04/2025-26) issued by the Urban Improvement Trust (UIT), Jaisalmer, for road renovation work.
Source reference: para 3.1The tender conditions mandated the submission of Earnest Money Deposit (EMD) via Demand Draft or Banker’s Cheque.
Source reference: no citationThe Appellant initially submitted EMD as lien-marked Fixed Deposit Receipts (FDRs), later substituting them with a Demand Draft on 23.08.2025, prior to the opening of technical bids.
Source reference: para 3.2The Respondents rejected the bid for non-compliance with the prescribed EMD mode.
Source reference: para 3.3A Single Judge of the High Court dismissed the Appellant's writ petition on 24.09.2025.
Source reference: para 3.4Meanwhile, the work order was issued to a third party on 18.09.2025, and work is currently in progress.
Source reference: para 3.5The Appellant challenged the dismissal via these intra-court appeals.
Source reference: no citationIssues
1. Whether the rejection of a bid due to the submission of EMD in a non-prescribed mode at the time of bid submission is legally sustainable despite subsequent rectification before technical evaluation.
Source reference: para 6.12. Whether the Court should interfere in a tender process under Article 226 when the contract has already been awarded and work has commenced.
Source reference: para 6.10, 6.11Law Applied
The Court applied Rule 42(6) of the Rajasthan Transparency in Public Procurement Rules, 2013, which specifies the mandatory modes for furnishing bid security.
Source reference: para 6.3It relied on the principle that essential tender conditions must be strictly enforced to ensure a level playing field.
Source reference: para 6.4The Court followed the precedents of *Central Coalfields Limited v. SLL-SML (Joint Venture Consortium)* (2016) 8 SCC 622, establishing that courts should not substitute administrative wisdom in contractual matters.
Source reference: para 6.5The Court followed the precedents of *Vidarbha Irrigation Development Corporation v. Anoj Kumar Garwala* (2020) 17 SCC 577, which limits the scope of judicial review in tender matters to the decision-making process rather than the merits.
Source reference: para 6.5, 6.9Reasoning
The Court reasoned that compliance with bid security conditions must exist at the time of submission; allowing post-submission rectifications would undermine the sanctity of the procurement process and disadvantage other bidders.
Source reference: para 6.4It distinguished *Poddar Steel Corporation* and *B.S.N. Joshi & Sons Ltd.*, noting that EMD requirements are not merely "ancillary" or "directory" but are fundamental to ensuring financial seriousness and procedural uniformity.
Source reference: para 6.6The Court found no evidence of Article 14 violations or discriminatory treatment, as the Appellant failed to prove that other similarly situated non-compliant bidders were accepted.
Source reference: para 6.7Crucially, the Court observed that because the Letter of Acceptance and work order were already issued and the project was underway, judicial restraint was necessary to avoid causing greater public injury by disrupting infrastructure development.
Source reference: para 6.10, 6.11Holding
The Court held that the rejection of the Appellant’s bid was neither arbitrary nor illegal, as the Appellant failed to meet a mandatory tender condition at the threshold.
The Court affirmed that judicial review is restricted to the decision-making process and found no procedural infirmity in the Respondent’s reasoned rejection order.
Source reference: para 6.8, 6.9Consequently, the Special Appeals were dismissed, and the order of the learned Single Judge was upheld.
Source reference: para 7Original Court PDF
M/s Bhati Constructions v. State of Rajasthan & Ors. [2026:RJ-JD:9474-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in