Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Manifest intention to arbitrate is a mandatory prerequisite for sustaining pre-arbitral interim relief under Section 9.

Premier Cables And Conductors Private Limitedv.Capital Trade Links Ltd.

Manifest intention to arbitrate is a mandatory prerequisite for sustaining pre-arbitral interim relief under Section 9.. Premier Cables And Conductors Private Limited vs Capital Trade Links Ltd.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether an application for interim measures under Section 9 of the Act can be permitted to remain pending indefinitely when the Petitioner fails to commence arbitral proceedings.

The court held

The Court held that the continuation of the proceedings was contrary to the object and scheme of the Act, as the Petitioner failed to take bona fide steps toward arbitration.

It also directed

The Court answered the core issues by ruling that a Section 9 petition cannot subsist in isolation or perpetuity without the commencement of arbitral proceedings.

Consequently, the High Court dismissed the petition and all pending applications.

No order was made as to costs.

01Facts

The Petitioner filed an application under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim injunctions against the Respondent concerning a loan agreement dated 08.07.2023.

¶ 1

Specifically, the Petitioner sought the deposit of the original agreement and orders restraining the Respondent from acting upon or creating third-party interests in the said agreement.

¶ 1

The petition remained pending before the High Court for approximately twenty months.

¶ 2

Although the Petitioner stated on 25.02.2025 that it was in the process of invoking arbitration, it failed to issue a notice under Section 21 of the Act or take steps to constitute an arbitral tribunal in the fourteen months following that statement.

¶ 5-6

02Issues

i.1. Whether an application for interim measures under Section 9 of the Act can be permitted to remain pending indefinitely when the Petitioner fails to commence arbitral proceedings.

¶ 7, 10

ii.2. Whether the Petitioner demonstrated a "manifest intention" to refer the dispute to arbitration as required for the exercise of jurisdiction under Section 9.

¶ 9, 12

03Law Applied

The Court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, which allows for interim measures but, under sub-section (2), contemplates the commencement of proceedings within ninety days of an interim order.

¶ 4, 14

It further relied on the precedent set by the Supreme Court in Sundaram Finance Ltd. v. NEPC India Ltd. (1999) 2 SCC 479, which held that a party seeking Section 9 relief before the commencement of arbitration must demonstrate a "manifest intention" to take recourse to arbitral proceedings.

¶ 11

The Court emphasized that Section 9 is an ancillary and facilitative remedy, not an independent substantive remedy.

¶ 8

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 17Section 21Section 36

04Reasoning

The Court reasoned that Section 9 jurisdiction is premised on the existence of a genuine intention to arbitrate within a reasonable period.

¶ 9

In this matter, the Petitioner’s twenty-month period of inaction and failure to issue a Section 21 notice despite previous representations to the Court militated against the foundational requirement of "manifest intention".

¶ 12

The Court observed that Section 9 should not be utilized as a parallel forum for litigants to secure tactical advantages or maintain ad-interim arrangements while indefinitely postponing the principal remedy.

¶ 10

Furthermore, the fact that the Petitioner never pressed for urgent interim directions during the pendency suggested a lack of imminent danger or pressing urgency.

¶ 13

The Court noted that even if no interim order was passed to trigger the 90-day limit in Section 9(2), the statutory framework does not grant a license for procedural indolence.

¶ 15-16

05Holding

The Court held that the continuation of the proceedings was contrary to the object and scheme of the Act, as the Petitioner failed to take bona fide steps toward arbitration.

¶ 18

The Court answered the core issues by ruling that a Section 9 petition cannot subsist in isolation or perpetuity without the commencement of arbitral proceedings.

¶ 10

Consequently, the High Court dismissed the petition and all pending applications.

¶ 19

No order was made as to costs.

¶ 20
Delhi High Court

Original Court PDF

Premier Cables And Conductors Private LimitedvsCapital Trade Links Ltd.

Delhi High Court · April 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment