Calcutta High CourtArbitration and MediationContract Law

MGO clauses are valid infrastructure cost recovery mechanisms and do not require proof of actual damage.

SRMB SRIJAN LIMITEDv.GREAT EASTERN ENERGY CORPORATION LIMITED

MGO clauses are valid infrastructure cost recovery mechanisms and do not require proof of actual damage.. SRMB SRIJAN LIMITED vs GREAT EASTERN ENERGY CORPORATION LIMITED. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the respondent-claimant failed to discharge its duty to mitigate losses as contemplated under Section 73 of the Indian Contract Act

The court held

The High Court dismissed the appeal and upheld the Single Judge’s order, confirming the arbitral award

It also directed

The court held that the Arbitral Tribunal took a plausible view of the contract and the nature of the CBM gas industry

It concluded that MGO clauses are valid mechanisms for infrastructure cost recovery and that overall profitability does not preclude a claim for damages arising from a specific breach of a supply contract

The prayer for stay of the judgment was refused

01Facts

The parties entered into a 25-year Gas Sale and Purchase Agreement (GSPA) in 2011 for the supply of coal bed methane (CBM gas)

¶ 2b

Clause 5.2 of the GSPA contained a "Minimum Guaranteed Offtake" (MGO) provision, requiring the Buyer (SRMB) to pay for 80% of the contracted quantity regardless of consumption, provided the Seller (GEECL) was ready to supply

¶ 2c

In 2014, SRMB sought a waiver of the MGO clause, which GEECL refused; subsequently, SRMB failed to renew a mandatory bank guarantee, leading GEECL to suspend supply

¶ 2g

SRMB terminated the agreement on July 07, 2014

¶ 2h

GEECL initiated arbitration, claiming MGO dues and damages. The Arbitral Tribunal awarded GEECL Rs. 58,50,45,169 plus interest, holding the termination illegal

¶ 2l

SRMB challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, but the challenge was dismissed by a Single Judge on September 05, 2024

¶ 3

SRMB then appealed under Section 37

¶ 1

02Issues

i.1. Whether the respondent-claimant failed to discharge its duty to mitigate losses as contemplated under Section 73 of the Indian Contract Act

¶ 11, Issue I

ii.2. Whether the respondent proved actual damages or loss to justify the MGO award, given its reported business profits

¶ 11, Issue II

iii.3. Whether the arbitral award was perverse for ignoring relevant financial evidence (CARE/CRISIL reports) and relying on extraneous observations from the Competition Commission

¶ 11, Issue III

03Law Applied

The court primarily applied Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996, which restrict judicial interference to cases of patent illegality or perversity where the arbitrator’s view is not even a "possible view"

¶ 10, 46

It relied on Sections 73 and 74 of the Indian Contract Act, 1872, regarding compensation for breach

¶ 4(x), 34

The court adopted the principle from Bihar State Electricity Board v. Green Rubber Industries and Shaila Bala Ray v. Darjeeling Municipality, which establishes that "minimum charge" or MGO clauses are intended to ensure a return on capital expenditure and infrastructure maintenance rather than being simple liquidated damages

¶ 29-30

It further applied the rule from Prafulla Ranjan Sarkar v. Hindusthan Building Society Ltd., stating the burden of proving a failure to mitigate loss lies on the party in breach

¶ 16

Provisions in the judgment · 14 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 23Section 28Section 31Section 34Section 37

Indian Contract Act, 1872 Section 73Section 74

Competition Act, 2002 Section 4Section 19Section 26Section 27Section 28Section 53Section 61

04Reasoning

The court rejected the mitigation argument because it was not raised before the Arbitral Tribunal and the appellant failed to provide evidence of what reasonable steps the respondent omitted

¶ 15, 17

Regarding the proof of loss, the court reasoned that CBM gas has no spot market and cannot be stored; if not consumed, it must be flared

¶ 22

The court found that even if the respondent’s overall business was profitable, the flaring of gas (evidenced by the appellant’s own exhibits) proved an actual loss of the specific bargain

¶ 20, 30

The court determined that the MGO clause serves as a "long-term insurance" for grid infrastructure costs and does not require mathematical proof of future loss

¶ 90

Finally, the court held that the non-consideration of CARE/CRISIL reports did not render the award perverse, as general profitability reports were not "vital evidence" capable of overturning the respondent's contractual entitlement to MGO payments

¶ 43-44

05Holding

The High Court dismissed the appeal and upheld the Single Judge’s order, confirming the arbitral award

¶ 49

The court held that the Arbitral Tribunal took a plausible view of the contract and the nature of the CBM gas industry

¶ 48

It concluded that MGO clauses are valid mechanisms for infrastructure cost recovery and that overall profitability does not preclude a claim for damages arising from a specific breach of a supply contract

¶ 30, 47

The prayer for stay of the judgment was refused

¶ 51
Calcutta High Court

Original Court PDF

SRMB SRIJAN LIMITEDvsGREAT EASTERN ENERGY CORPORATION LIMITED

Calcutta High Court · April 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment