01Facts
The petitioner challenged an order dated 12 April 2022 directing him to remove an alleged encroachment over municipal land at Sadar Bazar, Bhind. He asserted ownership and lawful construction, disputed the demarcation report, and alleged that his reply and documents had not been properly considered. The municipal authorities maintained that the encroachment was established by a Revenue Authority survey report and that the petitioner’s objections had been considered.
pp. 1–4The petitioner had earlier challenged a removal notice in W.P. No. 2668 of 2010, and a civil suit concerning part of the property had also resulted in a decree in favour of purchasers.
pp. 2–3This petition was filed in 2022; interim protection granted on 28 April 2022 remained in force while the case was pending.
p. 402Issues
i.1. Whether the Court should determine the parties’ competing claims concerning encroachment, title, possession, and the accuracy of the demarcation report.
pp. 4–5ii.2. Whether the impugned removal order should be quashed because the proposed demolition had lost its efficacy during the pendency of the petition and the continuing interim protection.
pp. 4–503Law Applied
The petition invoked Articles 226 and 227 of the Constitution of India, which empower the High Court to exercise writ and supervisory jurisdiction.
p. 1The Court did not rely on any cited precedent or decide a substantive rule concerning title or encroachment. It directed that any fresh proceedings must be conducted in accordance with law, with a reasonable opportunity of hearing, consideration of the petitioner’s objections and documents, and a reasoned order.
pp. 5–604Reasoning
The Court noted that the petition had remained pending since 2022 and that interim protection against action under the impugned order had continued throughout. It concluded that the proposed demolition had, by passage of time, lost its efficacy and that further adjudication of the controversy surrounding that order would serve no useful purpose.
p. 4The Court therefore expressly refrained from deciding the competing claims concerning encroachment, title, possession, or the demarcation report.
pp. 4–505Holding
The Court quashed the order dated 12 April 2022, without expressing any opinion on the merits of the dispute.
pp. 5–6It allowed the petition and granted the Chief Municipal Officer liberty to initiate fresh proceedings and issue a fresh notice, if warranted. Any such proceedings must afford the petitioner a reasonable hearing, consider his objections and relevant documents, and culminate in a reasoned order in accordance with law.
p. 6Original Court PDF
Rupesh BansalvsThe State Of Madhya Pradesh
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in