01Facts
The Tehsildar, Mehgaon, passed an order dated 29 April 2025 in proceedings under Section 248 of the Madhya Pradesh Land Revenue Code, 1959 (MPLRC).
¶ 2The Sub-Divisional Officer dismissed the petitioners’ appeal on 6 August 2025.
¶ 2The petitioners’ revision under Section 50 MPLRC was rejected by the Collector on 16 July 2026 as not maintainable, relying on Section 50(2)(a).
¶ 3The petitioners challenged that rejection under Article 226, contending that no second appeal lay under Section 46(b) and that the Collector should have addressed the Tehsildar’s competence to make an order concerning settlement or grant of patta.
¶ 3–4The State defended the Collector’s decision.
¶ 502Issues
i.Whether the Collector erred by rejecting the revision on maintainability grounds without determining the Tehsildar’s jurisdiction and competence to pass the original order.
¶ 6–8ii.Whether, if the Tehsildar lacked competence, the matter should be referred to the authority legally competent to decide the settlement or grant of patta.
¶ 7–9iii.Whether interim protection against coercive action should be granted pending reconsideration.
¶ 10–1203Law Applied
Section 248 MPLRC was the basis of the original proceedings; Sections 46(b) and 50 governed the petitioners’ appeal and revision, while Section 50(2)(a) was relied on by the Collector in rejecting the revision.
¶ 2–4The Court applied the principle that an order made without jurisdiction or beyond an authority’s statutory powers cannot be sustained, because the decision-maker’s competence goes to the root of the matter and must be examined.
¶ 7Provisions in the judgment · 3 · Linked ones open on LawLens
MP Land Revenue Code 1959 Section 50Section 248Section 46
04Reasoning
The Collector’s order referred to a circular indicating that the Tehsildar might not have authority to make an order concerning settlement or grant of patta, but did not determine the precise scope of the Tehsildar’s jurisdiction or identify the competent authority.
¶ 6–7The Court held that the matter therefore required reconsideration: the Collector must first determine the Tehsildar’s competence and, if it was lacking, identify the legally competent authority and remit the matter to it for a fresh decision after hearing the parties.
¶ 7–9The Court did not decide the merits of the underlying dispute.
¶ 1305Holding
The writ petition was allowed.
¶ 8–9, 14The Collector’s order dated 16 July 2026 was set aside, and the matter was remitted for reconsideration in accordance with the Court’s directions.
¶ 8–9, 14The Collector was directed to decide the interim-relief application, preferably within seven days of receiving the certified order; meanwhile, respondents were restrained from taking coercive action to remove the alleged encroachment pursuant to the 2025 orders without following due process.
¶ 10–11The Collector was also directed to consider the High Court’s earlier order dated 7 July 2026 in Review Petition No. 1247 of 2026 when deciding interim relief.
¶ 12Original Court PDF
Manoj SharmavsThe State Of Madhya Pradesh