Calcutta High CourtAdministrative and Public LawConstruction Law

Municipal authorities must adjudicate alleged illegal construction under Section 218 by a reasoned order.

SUBHANKAR CHOWDHURYv.THE KONNAGAR MUNICIPALITY AND ORS.

Municipal authorities must adjudicate alleged illegal construction under Section 218 by a reasoned order.. SUBHANKAR CHOWDHURY vs THE KONNAGAR MUNICIPALITY AND ORS.. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the municipal authorities were required to initiate statutory proceedings in view of the prima facie deviations from the sanctioned building plan.

The court held

The Court disposed of WPA 12447 of 2025 by directing Konnagar Municipality to initiate proceedings under Section 218 of the West Bengal Municipal Act, 1993, undertake any further inspection in the presence of the parties, determine the sanctioned and actual construction floor-wise, circulate its report, and pass a reasoned order expeditiously.

It also directed

No further construction was permitted until the municipal decision, and a notice regarding the prima facie illegal construction was directed to be displayed at the premises.

WPA 12447 of 2025 was accordingly disposed of.

WPA 24956 of 2026, challenging cancellation of the completion certificate, was also disposed of because the first petition had been disposed of and the alleged illegal construction was to be examined in the statutory proceedings; the Court made clear that the finding of illegality was only prima facie at that stage.

01Facts

The first writ petition challenged alleged illegal construction at Holding No. 29, Rammohan Place, Ward No. 17, under Konnagar Municipality, and sought an enquiry and report by the municipal authorities.

¶ 1

Although the first petitioner sought to withdraw the petition, the Court declined to permit withdrawal because the matter concerned alleged illegal construction, which the Court regarded as a social evil.

¶ 2

The Municipality thereafter conducted an inspection and filed its report.

¶ 3

The report disclosed that the sanctioned plan permitted construction from the ground floor to the fifth floor, with specified mandatory open spaces and a sanctioned building height of 17.10 metres.

¶ 7

The inspection allegedly revealed deviations in the open spaces on the northern, western and eastern sides from the first to the fifth floors.

¶ 7

The report also did not clearly set out the entire constructed covered area.

¶ 8

The second writ petition was filed by the developer/owner challenging the purported unilateral cancellation of the completion certificate relating to the same premises.

¶ 4 · ¶ 6

It was contended that the cancellation had been effected without notice or an opportunity of hearing and without adequate reasons.

¶ 4 · ¶ 6

Since both petitions concerned the same premises and overlapping issues, the Court heard them together.

¶ 5

02Issues

i.Whether the municipal authorities were required to initiate statutory proceedings in view of the prima facie deviations from the sanctioned building plan.

¶ 7–9

ii.Whether the Municipality could cancel the completion certificate without providing the affected party an opportunity of hearing and without furnishing reasons.

¶ 6

iii.What directions should be issued for determining the sanctioned and actually constructed areas and for regulating further construction pending the municipal decision.

¶ 9–12

03Law Applied

The Court primarily applied Section 218 of the West Bengal Municipal Act, 1993, directing the municipal authorities to initiate proceedings under that provision and bring them to a reasoned conclusion.

¶ 9

The Court also applied the principles of natural justice, particularly the requirement of notice and a meaningful opportunity to respond before an adverse municipal decision is taken, directing that the inspection report be circulated to the parties before the decision.

¶ 10

The Court further relied on the general administrative-law requirement that statutory authorities pass a reasoned order based on relevant materials.

No judicial precedent was cited in the judgment.

Provisions in the judgment · 1 · Linked ones open on LawLens

West Bengal Municipal Act, 1993 Section 218

04Reasoning

The municipal inspection disclosed apparent departures from the sanctioned open spaces: the northern ground-floor setback was stated to be 1.20 metres instead of 3.00 metres, while the setbacks on the northern, western and eastern sides on the upper floors were also less than those reflected in the sanctioned plan.

¶ 7

The Court additionally noted that the municipal report did not fully identify the constructed covered area.

¶ 8

Since these matters required factual determination and had not been finally adjudicated, the Court did not itself declare the construction illegal.

¶ 9–10

Instead, it directed the Municipality to commence proceedings under Section 218, conduct any further inspection necessary in the presence of the parties, ascertain the exact sanctioned and constructed areas floor-wise, circulate the inspection report, and pass a reasoned order.

¶ 9–10

The directions also ensured procedural fairness in relation to the developer’s challenge to the completion certificate.

¶ 10

Pending that determination, the Court restrained further construction and directed the Municipality to paste a notice on the outer wall recording the prima facie nature of the alleged illegal construction.

¶ 11–12

05Holding

The Court disposed of WPA 12447 of 2025 by directing Konnagar Municipality to initiate proceedings under Section 218 of the West Bengal Municipal Act, 1993, undertake any further inspection in the presence of the parties, determine the sanctioned and actual construction floor-wise, circulate its report, and pass a reasoned order expeditiously.

¶ 9–10

No further construction was permitted until the municipal decision, and a notice regarding the prima facie illegal construction was directed to be displayed at the premises.

¶ 11–12

WPA 12447 of 2025 was accordingly disposed of.

¶ 13

WPA 24956 of 2026, challenging cancellation of the completion certificate, was also disposed of because the first petition had been disposed of and the alleged illegal construction was to be examined in the statutory proceedings; the Court made clear that the finding of illegality was only prima facie at that stage.

¶ 14
Calcutta High Court

Original Court PDF

SUBHANKAR CHOWDHURYvsTHE KONNAGAR MUNICIPALITY AND ORS.

Calcutta High Court · September 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment