Delhi High CourtAdministrative and Public LawConstruction Law

NHAI Must Reconsider Debarment of Hamirpur Bypass Firms After Fatal Bridge Collapse, Delhi HC Says Hearing Was Denied

M/S Hamirpur Byepass Private Ltd & Anr.v.National Highway Authority Of India & Anr.

NHAI Must Reconsider Debarment of Hamirpur Bypass Firms After Fatal Bridge Collapse, Delhi HC Says Hearing Was Denied. M/S Hamirpur Byepass Private Ltd & Anr. vs National Highway Authority Of India & Anr.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the impugned debarment order is vitiated by violation of natural justice, where the TEC report relied upon was not furnished and no personal hearing was afforded despite a specific request.

The court held

The impugned order suffers from procedural deficiencies because the TEC report was not furnished and no personal hearing was granted, and the explanation offered was unsatisfactory.

It also directed

At this stage, the Court declined to set aside the order or interdict its operation altogether, given the gravity of the incident.

Respondent No. 1 was directed to (i) furnish the TEC report and all other proposed material within one week; (ii) afford the petitioners a reasonable opportunity to respond and an effective personal hearing; and (iii) reconsider the matter independently and pass a fresh reasoned order within four weeks.

The impugned order remains operative, but will automatically stand vacated, insofar as it operates against the petitioners, if no fresh order is passed within four weeks. The petition is disposed of accordingly, with the merits left open.

01Facts

The petitioners challenged an order dated 17.11.2026 by which Petitioner No. 2 was debarred from future National Highways bids under MoRTH and NHAI for three years or until completion of rectification, whichever is later, and Petitioner No. 1 was fined ₹3,97,50,000.

¶ 1

Petitioner No. 1, an SPV, had executed a Concession Agreement for a Hybrid Annuity Mode highway project at Hamirpur Bypass on 24.11.2022.

¶ 2

On 02.10.2026, while the launching nose was being lifted to correct a lateral displacement of a sliding shoe, the 90 m truss and launching nose collapsed, killing one worker and injuring three others.

¶ 3

A show cause notice dated 12.10.2026 proposed debarment for up to three years.

¶ 4

The petitioners replied on 27.10.2026 and specifically sought a personal hearing.

¶ 4, 7

A Technical Expert Committee (TEC) report dated 23.10.2026 was constituted and relied upon in the impugned order.

¶ 4, 6

It is undisputed that the TEC report was not furnished to the petitioners and that no hearing was granted.

¶ 11

The respondents justified this on the ground that certain documents sought from the petitioners were not furnished.

¶ 9, 11

02Issues

i.1. Whether the impugned debarment order is vitiated by violation of natural justice, where the TEC report relied upon was not furnished and no personal hearing was afforded despite a specific request.

¶ 6, 7, 11

ii.2. Whether the non-furnishing of documents by the petitioners justifies proceeding without a hearing, and whether the procedural lapses warrant quashing the order given the gravity of the incident.

¶ 9, 12, 14–16

iii.3. Whether the appropriate relief is remand for fresh consideration, and whether the impugned order should be stayed pending such reconsideration.

¶ 16–21

03Law Applied

The judgment cites no statute, rule, or precedent by name. The Court applied the principles of natural justice, namely that an affected party must be furnished the material relied upon and afforded a meaningful opportunity to meet the case against it before an adverse decision is taken.

¶ 12, 13

A request for personal hearing is a material element of the opportunity to be heard, which the authority cannot render redundant merely because some documents were not supplied.

¶ 12

An order imposing serious consequences such as debarment must rest on a process affording meaningful opportunity to respond.

¶ 13

The discretionary power to remand for fresh decision may be exercised while withholding interim stay, having regard to the severity of the allegations and public safety concerns.

¶ 14, 17, 21

04Reasoning

The Court accepted that the procedural breach was established on the undisputed record: the TEC report was not supplied and no hearing was granted.

¶ 11

The respondents' explanation based on the petitioners' failure to produce documents was found unsatisfactory, since the authority could have identified the required documents, sought them, and then heard the petitioners.

¶ 12

Because the debarment carries grave consequences, the procedural defects were not treated as trivial.

¶ 12, 13

The Court weighed these defects against the fatal nature of the incident (one death, three injuries) and the substantive observations in the TEC report regarding absent inspection and clearance mechanisms, absence of a site engineer, and non-adherence to safety protocols.

¶ 14, 15

The TEC had not conclusively determined the trigger of the collapse, but the observations on execution were found to be serious and could not be disregarded.

¶ 15

On that balance, the Court declined to quash the order outright and instead chose remand, so that the authority could cure the defect by supplying material, hearing the petitioners, and deciding afresh.

¶ 16, 17

The Court declined to suspend the order, given the severity of the allegations, but imposed a deemed-vacation condition if no fresh order was passed within four weeks.

¶ 21

05Holding

The impugned order suffers from procedural deficiencies because the TEC report was not furnished and no personal hearing was granted, and the explanation offered was unsatisfactory.

¶ 11, 12

At this stage, the Court declined to set aside the order or interdict its operation altogether, given the gravity of the incident.

¶ 14, 15, 16

Respondent No. 1 was directed to (i) furnish the TEC report and all other proposed material within one week; (ii) afford the petitioners a reasonable opportunity to respond and an effective personal hearing; and (iii) reconsider the matter independently and pass a fresh reasoned order within four weeks.

¶ 18, 19, 20

The impugned order remains operative, but will automatically stand vacated, insofar as it operates against the petitioners, if no fresh order is passed within four weeks. The petition is disposed of accordingly, with the merits left open.

¶ 21, 22, 23
Delhi High Court

Original Court PDF

M/S Hamirpur Byepass Private Ltd & Anr.vsNational Highway Authority Of India & Anr.

Delhi High Court · November 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment