01Facts
The petitioner executed a contract agreement with the National Highways Authority of India (Respondent No. 1) on 10.02.2021 for construction of a six-lane access-controlled greenfield highway (Km 99.000 to Km 130.73, Rajasthan/Gujarat Border to Santalpur, NH-754K) under Bharatmala Pariyojana (Phase I).
¶ 4The petitioner asserts that commercial use of the highway began on 01.04.2025, though no provisional completion certificate was issued.
¶ 4Following social media posts alleging pavement distress, Respondent No. 1 issued a show cause notice dated 02.07.2025 proposing debarment for one year or until rectification of the stretch.
¶ 2, 4The show cause notice dated 02.07.2025 also imposed an immediate suspension from ongoing and future bidding for one month or until successful demonstration of pavement crust compliance.
¶ 2, 4A press release dated 03.07.2025 stated that the petitioner stood debarred.
¶ 5The petitioner replied on 17.07.2025 describing remediation work.
¶ 6A second show cause notice dated 22.09.2025 called on the petitioner to explain why it should not be declared a "non-performer" until rectification, and recorded that the suspension would continue.
¶ 3, 6The petitioner replied on 06.10.2025.
¶ 6The petitioner contended that no decision had been taken on either notice for over a year, and that it remained effectively debarred.
¶ 7Respondent No. 1 contended that the petitioner was never debarred, only suspended, and that the suspension continued because defects were not rectified.
¶ 8The parties agreed that the facts were undisputed.
¶ 1, 902Issues
i.1. Whether the suspension imposed under the show cause notice dated 02.07.2025, which continued for over one year, amounts to debarment in substance, such that the one-year maximum penalty proposed has already been exhausted.
¶ 9–10, 12ii.2. Whether administrative show cause notices may remain operative indefinitely in the absence of any final decision, where the respondents have not shown that rectification is pending or the highway is non-functional.
¶ 9, 11–1203Law Applied
The judgment cites no statute, contractual clause, or precedent.
A suspension from participating in bidding that continues for an extended period is substantively equivalent to debarment, regardless of the label the authority attaches to it.
¶ 9A show cause notice is an administrative action and cannot be permitted to operate in perpetuity, particularly where the authority has not decided it and has not shown that the underlying defect remains unremedied.
¶ 11–12The contractual framework (the 10.02.2021 contract agreement) is noted as the source of the petitioner's obligations but is not interpreted.
¶ 404Reasoning
The Court declined to examine the merits of the pavement-distress allegations and focused on the duration and effect of the measures.
¶ 10The one-month suspension, expressly tied to demonstrating compliance, had continued for more than a year and effectively operated as a bar on bidding, which the Court treated as akin to the one-year debarment proposed in the first notice.
¶ 9Because the proposed maximum penalty of one year had already elapsed, the petitioner had, in the Court's view, "already suffered the maximum penalty".
¶ 12The Court found that the respondents had not shown any pending rectification or non-functionality of the highway, and held that any remaining remedial steps could be pursued through appropriate action by the authority, and that the respondents' bare assertion that defects persisted could not sustain the notices indefinitely.
¶ 11The absence of any decision on either notice over more than a year was treated as decisive in favour of the petitioner.
¶ 7, 9–1005Holding
The suspension, continuing for more than one year without decision, was akin to debarment, and the maximum one-year penalty proposed in the notice of 02.07.2025 had already been suffered.
¶ 9, 12Show cause notices of this kind cannot operate indefinitely in the absence of a decision or demonstrated continuing defect.
¶ 11–12The Court set aside the show cause notices dated 02.07.2025 and 22.09.2025 and allowed the writ petition, disposing of the pending applications.
¶ 12–13The judgment does not expressly preclude the authority from taking fresh action in accordance with law for any remaining remedial measures.
¶ 11Original Court PDF
M/S Cds Infra Projects LimitedvsNational Highways Authority Of India & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in