Facts
The petitioner applied for approval to establish a new Concrete Sleeper Plant (CSP) in Bilaspur, Chhattisgarh, on April 1, 2025
Source reference: para. 3Although the petitioner claims to have completed all formalities and submitted requisite documents by March 2026, the Railway authorities have not yet granted formal approval.
Source reference: para. 4During the pendency of the application, the Ministry of Railways (RDSO) issued new guidelines/instructions (dated May 22, 2026) providing a one-time extension until December 31, 2026/2027, for existing or stabilized CSPs to commission railway sidings.
Source reference: para. 4The petitioner approached the High Court seeking a writ of mandamus to compel the respondents to grant provisional approval and extend the siding commissioning deadline to them, arguing they should be treated at par with existing plants.
Source reference: para. 2, 5The respondents contended that the petitioner, as a new entrant without existing approval, is governed by stricter extant policies requiring a functional siding for initial approval.
Source reference: para. 6Issues
1. Whether a writ of mandamus can be issued to grant "deemed approval" or compel technical certification of a Concrete Sleeper Plant by the High Court under Article 226.
Source reference: para. 82. Whether a new applicant for a CSP is entitled to the benefit of relaxation/extension for commissioning railway sidings provided under the guidelines dated May 22, 2026, which are specifically applicable to existing or stabilized plants.
Source reference: para. 9, 10Law Applied
The court applied the principle of judicial restraint in technical matters, noting that a writ of mandamus cannot be issued to bypass statutory or robust administrative mechanisms involving technical assessments.
Source reference: para. 8Administrative relaxations or specific policy guidelines must be interpreted strictly according to their eligibility criteria; here, the guidelines distinguished between "existing/stabilized CSPs" and "new applicants".
Source reference: para. 9, 10The court also reaffirmed that there is no concept of "deemed approval" in such complex regulatory frameworks.
Source reference: para. 10Reasoning
The court reasoned that granting the requested relief would constitute a "deemed approval," which is impermissible given the multi-stage technical scrutiny required, including mix design approval, sample testing, and capacity evaluation.
Source reference: para. 8The court emphasized its lack of technical expertise to substitute the satisfaction of the approving authority.
Source reference: para. 8Regarding the 2026 guidelines, the court found the petitioner's reliance "misplaced" because the relaxation was a limited concession for plants already in operation or previously approved under the 2021 policy.
Source reference: para. 9, 10Since the petitioner’s plant was not yet approved or stabilized, they remained governed by the standard requirement that a railway siding must be ready for use prior to the grant of approval.
Source reference: para. 9The court viewed the petition as an attempt to achieve indirectly (approval) what the petitioner had not yet secured through the formal regulatory process.
Source reference: para. 10Holding
The High Court held that the petitioner is not entitled to the benefit of the extension meant for existing CSPs and that no mandamus can be issued to grant approval where technical assessments are pending.
The petition was dismissed for lack of merit, though the court clarified that the authorities may decide the pending application on its own merits in accordance with the law.
Source reference: para. 11Original Court PDF
M/S Calcutta Springs Limited Thru. Authorized Signatory Nirmal Kumar GopevsU.O.I. Thru. Its Secy. Ministry Of Railways New Delhi And Another
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in