Delhi High Court
Tax LawArbitration and Mediation

No extra stamp duty is payable on a Gujarat arbitral award merely because enforcement is sought in Delhi, rules Delhi HC

Kirloskar Pneumatic Company Limited vs Oil And Natural Gas Corporation Limited

Delhi High CourtJUDGMENT: October 09, 20263 MIN READSOURCE JUDGMENT
No extra stamp duty is payable on a Gujarat arbitral award merely because enforcement is sought in Delhi, rules Delhi HC. Kirloskar Pneumatic Company Limited vs Oil And Natural Gas Corporation Limited. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Decree Holder sought enforcement under Section 36 of the Arbitration and Conciliation Act, 1996 of an arbitral award dated 13 April 2023, as corrected on 15 April 2023.

Source reference: pp. 1–3

The award was signed at Ahmedabad, Gujarat, and stamped under the Gujarat Stamp Act, 1958.

Source reference: pp. 1–3

The Judgment Debtor objected that the award attracted differential stamp duty under the Indian Stamp Act, 1899, as applicable in Delhi, and that payment of the differential amount was late.

Source reference: pp. 1–3

The Decree Holder had deposited an amount calculated at Delhi rates, although it disputed any obligation to do so.

Source reference: p. 22

The award’s interest component had been set aside in Section 34 proceedings, and an appeal under Section 37 was pending; the remaining amount payable was Rs. 3,78,22,968.

Source reference: pp. 23–24
02

Issues

1. Whether an arbitral award executed and stamped in Gujarat attracts additional or differential stamp duty merely because enforcement is sought in Delhi.

Source reference: pp. 9–11, 18–22

2. Whether the alleged late payment of differential stamp duty rendered the award insufficiently stamped or prevented its enforcement.

Source reference: pp. 2, 6–9

3. Whether the Decree Holder could withdraw the amount remaining payable under the award while the Section 37 appeal was pending.

Source reference: pp. 23–24
03

Law Applied

Under Sections 2(12) and 17 of the Indian Stamp Act, 1899, “execution” of an instrument means signing it, and an instrument executed in India must be stamped before or at the time of execution.

Source reference: pp. 4–5, 10

Sections 33, 35 and 38 require a court to address an insufficiently stamped instrument in accordance with the Act when the issue arises at enforcement; the sufficiency of stamping is relevant at that stage, but enforcement is not itself a chargeable event.

Source reference: pp. 6–10

Under New Central Jute Mills Co. Ltd. v. State of W.B., a second State may impose differential duty where its applicable legislation creates a further charge upon receipt of an instrument with the required territorial or transactional nexus.

Source reference: pp. 11–18

Genus Power and Infrastructures Ltd. v. Supreme Advertising Pvt. Ltd. clarified that statutory “execution” is not synonymous with enforcement, while M/s URC Construction (P) Ltd. v. Airports Authority of India addressed the enforcement-stage duty to examine stamping and the statutory procedure for insufficiently stamped instruments.

Source reference: pp. 3–9

The award was assessed under Article 13 of Schedule I to the Gujarat Stamp Act, 1958.

Source reference: p. 22
04

Reasoning

The Court distinguished the event that makes an instrument chargeable—here, signing the award in Gujarat—from the later stage at which a court may examine whether it is sufficiently stamped. Although stamp sufficiency may be considered during enforcement, that does not create a fresh liability when enforcement is brought in another State.

Source reference: pp. 9–11

New Central Jute Mills did not support the Judgment Debtor absent a Delhi statutory provision imposing additional duty upon receipt or enforcement of an out-of-State instrument. No such provision under the Indian Stamp Act as applicable in Delhi was identified; the Court therefore declined to imply a fiscal liability.

Source reference: pp. 11–22

Since no differential duty was legally payable, the objection based on the alleged delay in paying it did not defeat enforcement. The Court found the award sufficiently stamped under Gujarat law.

Source reference: p. 22

As to disbursement, it made withdrawal conditional on an undertaking and indemnity bond because the Section 37 appeal remained pending.

Source reference: pp. 23–24
05

Holding

The Court held that enforcement in Delhi did not create an additional liability to pay differential stamp duty and rejected the Judgment Debtor’s insufficiency-of-stamp-duty objection.

It disposed of the enforcement petition, permitting the Decree Holder to withdraw Rs. 3,78,22,968 upon furnishing the required undertaking and indemnity bond to the satisfaction of the Registrar General; the parties retained liberty to seek revival after the Section 37 appeal was decided.

Source reference: pp. 23–24

The Judgment Debtor’s application for refund of the excess amount deposited was allowed, with the Registry directed to refund it in accordance with applicable rules and procedure.

Source reference: p. 24
06

Acts & Sections Cited

21 provisions across 5 statutes referred to in this judgment. Each provision opens on LawLens.

Indian Stamp Act, 189910 provisions

Bombay Stamp Act, 19581

Maharashtra Stamp Act2

KARNATAKA STAMP ACT, 19571

Delhi High Court

Original Court PDF

Kirloskar Pneumatic Company LimitedvsOil And Natural Gas Corporation Limited

Delhi High Court · October 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment