Facts
PEDA invited bids in 2009 for a 500 kW Mini Hydel Project at Terkiana, assuring a water discharge of 350 cusecs in the Holy Bein rivulet
Source reference: p. 5APPL won the bid by offering PEDA an "energy share" of 20% for 10 years and 30% thereafter
Source reference: p. 5After commissioning on August 31, 2010, the plant was shut down in January 2011 due to local protests over water-logging caused by the 350-cusec discharge, which the rivulet could not handle
Source reference: p. 6To resolve this, a Tripartite Agreement (TPA) was signed on August 10, 2011, for APPL to construct an "Escape Channel"
Source reference: p. 6Clause 15 of the TPA stated APPL would bear the construction costs
Source reference: p. 29APPL subsequently petitioned PSERC for tariff re-determination, citing increased project costs and seeking a waiver of the energy share
Source reference: p. 7PSERC refused to re-determine the tariff but ordered that the Escape Channel costs (without interest) be recovered from PEDA’s energy share
Source reference: p. 7-8Both PEDA and APPL appealed this order
Source reference: p. 8Issues
1. Whether the construction of the Escape Channel constitutes a Force Majeure event warranting the addition of its cost to the capital cost for tariff re-determination.
Source reference: p. 232. Whether PEDA is liable to compensate APPL for the cost of the Escape Channel despite Clause 15 of the Tripartite Agreement.
Source reference: p. 273. Whether the State Commission acted within its jurisdiction under Section 86(1)(a) of the Electricity Act, 2003, by adjusting compensation against PEDA’s energy share.
Source reference: p. 314. Whether APPL is entitled to additional compensation for interest, O&M expenses, and carrying costs during the project shutdown.
Source reference: p. 33Law Applied
The court applied Section 86(1)(a) of the Electricity Act, 2003, which empowers the State Commission to determine the tariff for generation and supply
Source reference: p. 31It relied on the principle of "economic duress," holding that contracts signed under financial vulnerability and dominant bargaining positions may be reviewed for equity
Source reference: p. 29The court further applied administrative law principles regarding tender transparency, asserting that an inviting agency is bound by the technical assurances (e.g., water discharge) provided in bid documents
Source reference: p. 26It also cited Gujarat Urja Vikas Nigam Ltd. v. Essar Power Limited to affirm the Commission's jurisdiction over such disputes
Source reference: p. 18Reasoning
The Tribunal found that the inability of the Holy Bein to handle 350 cusecs was not a Force Majeure event but a failure of due diligence by PEDA during the bidding stage
Source reference: p. 26Consequently, while the generic tariff could not be re-determined as it was part of a competitive bid process, APPL deserved compensation for unforeseen infrastructure costs
Source reference: p. 26, 31The Tribunal observed that APPL signed the TPA under "economic duress" while its plant was shut down, meaning Clause 15 did not bar compensation
Source reference: p. 29PEDA, having derived a commercial advantage (the energy share) based on a flawed technical premise, was held liable
Source reference: p. 31The Tribunal rejected PEDA’s argument that APPL could be compensated via "20% extra generation," noting that machines designed for 350 cusecs cannot safely or efficiently produce extra power simply by increasing water flow
Source reference: p. 32-33Finally, the Tribunal held that while the principal cost was recoverable, APPL could not claim interest or O&M expenses as it had not timely protested the costs post-TPA
Source reference: p. 34Holding
The Tribunal upheld the PSERC order with modifications.
Tariff re-determination is denied
Source reference: p. 26APPL is entitled to the actual cost of the Escape Channel (without interest)
Source reference: p. 35This cost must be adjusted against PEDA’s energy share
Source reference: p. 35PEDA cannot transfer its share to PSPCL until APPL is fully compensated
Source reference: p. 35The matter was remanded to PSERC to conduct a "prudence check" to finalize the actual construction costs incurred by APPL
Source reference: p. 34-35All pending applications were disposed of
Source reference: p. 35Original Court PDF
PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA)vsPUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in