APTELAdministrative and Public LawContract Law

Nodal agency liable for additional costs necessitated by inaccurate tender specifications despite subsequent restrictive contractual terms.

PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA)v.PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors

Nodal agency liable for additional costs necessitated by inaccurate tender specifications despite subsequent restrictive contractual terms.. PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA) vs PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors. APTEL. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the construction of the Escape Channel constitutes a Force Majeure event warranting the addition of its cost to the capital cost for tariff re-determination.

The court held

The Tribunal upheld the PSERC order with modifications.

It also directed

Tariff re-determination is denied

APPL is entitled to the actual cost of the Escape Channel (without interest)

This cost must be adjusted against PEDA’s energy share

PEDA cannot transfer its share to PSPCL until APPL is fully compensated

The matter was remanded to PSERC to conduct a "prudence check" to finalize the actual construction costs incurred by APPL

All pending applications were disposed of

01Facts

PEDA invited bids in 2009 for a 500 kW Mini Hydel Project at Terkiana, assuring a water discharge of 350 cusecs in the Holy Bein rivulet

p. 5

APPL won the bid by offering PEDA an "energy share" of 20% for 10 years and 30% thereafter

p. 5

After commissioning on August 31, 2010, the plant was shut down in January 2011 due to local protests over water-logging caused by the 350-cusec discharge, which the rivulet could not handle

p. 6

To resolve this, a Tripartite Agreement (TPA) was signed on August 10, 2011, for APPL to construct an "Escape Channel"

p. 6

Clause 15 of the TPA stated APPL would bear the construction costs

p. 29

APPL subsequently petitioned PSERC for tariff re-determination, citing increased project costs and seeking a waiver of the energy share

p. 7

PSERC refused to re-determine the tariff but ordered that the Escape Channel costs (without interest) be recovered from PEDA’s energy share

pp. 7-8

Both PEDA and APPL appealed this order

p. 8

02Issues

i.1. Whether the construction of the Escape Channel constitutes a Force Majeure event warranting the addition of its cost to the capital cost for tariff re-determination.

p. 23

ii.2. Whether PEDA is liable to compensate APPL for the cost of the Escape Channel despite Clause 15 of the Tripartite Agreement.

p. 27

iii.3. Whether the State Commission acted within its jurisdiction under Section 86(1)(a) of the Electricity Act, 2003, by adjusting compensation against PEDA’s energy share.

p. 31

iv.4. Whether APPL is entitled to additional compensation for interest, O&M expenses, and carrying costs during the project shutdown.

p. 33

03Law Applied

The court applied Section 86(1)(a) of the Electricity Act, 2003, which empowers the State Commission to determine the tariff for generation and supply

p. 31

It relied on the principle of "economic duress," holding that contracts signed under financial vulnerability and dominant bargaining positions may be reviewed for equity

p. 29

The court further applied administrative law principles regarding tender transparency, asserting that an inviting agency is bound by the technical assurances (e.g., water discharge) provided in bid documents

p. 26

It also cited Gujarat Urja Vikas Nigam Ltd. v. Essar Power Limited to affirm the Commission's jurisdiction over such disputes

p. 18

04Reasoning

The Tribunal found that the inability of the Holy Bein to handle 350 cusecs was not a Force Majeure event but a failure of due diligence by PEDA during the bidding stage

p. 26

Consequently, while the generic tariff could not be re-determined as it was part of a competitive bid process, APPL deserved compensation for unforeseen infrastructure costs

p. 26, 31

The Tribunal observed that APPL signed the TPA under "economic duress" while its plant was shut down, meaning Clause 15 did not bar compensation

p. 29

PEDA, having derived a commercial advantage (the energy share) based on a flawed technical premise, was held liable

p. 31

The Tribunal rejected PEDA’s argument that APPL could be compensated via "20% extra generation," noting that machines designed for 350 cusecs cannot safely or efficiently produce extra power simply by increasing water flow

pp. 32-33

Finally, the Tribunal held that while the principal cost was recoverable, APPL could not claim interest or O&M expenses as it had not timely protested the costs post-TPA

p. 34

05Holding

The Tribunal upheld the PSERC order with modifications.

Tariff re-determination is denied

p. 26

APPL is entitled to the actual cost of the Escape Channel (without interest)

p. 35

This cost must be adjusted against PEDA’s energy share

p. 35

PEDA cannot transfer its share to PSPCL until APPL is fully compensated

p. 35

The matter was remanded to PSERC to conduct a "prudence check" to finalize the actual construction costs incurred by APPL

pp. 34-35

All pending applications were disposed of

p. 35
APTEL

Original Court PDF

PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA)vsPUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors

APTEL · March 24, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment