APTEL

Nodal agency liable for additional costs necessitated by inaccurate tender specifications despite subsequent restrictive contractual terms.

PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA) vs PUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors

APTELJUDGMENT: March 24, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

PEDA invited bids in 2009 for a 500 kW Mini Hydel Project at Terkiana, assuring a water discharge of 350 cusecs in the Holy Bein rivulet

Source reference: p. 5

APPL won the bid by offering PEDA an "energy share" of 20% for 10 years and 30% thereafter

Source reference: p. 5

After commissioning on August 31, 2010, the plant was shut down in January 2011 due to local protests over water-logging caused by the 350-cusec discharge, which the rivulet could not handle

Source reference: p. 6

To resolve this, a Tripartite Agreement (TPA) was signed on August 10, 2011, for APPL to construct an "Escape Channel"

Source reference: p. 6

Clause 15 of the TPA stated APPL would bear the construction costs

Source reference: p. 29

APPL subsequently petitioned PSERC for tariff re-determination, citing increased project costs and seeking a waiver of the energy share

Source reference: p. 7

PSERC refused to re-determine the tariff but ordered that the Escape Channel costs (without interest) be recovered from PEDA’s energy share

Source reference: p. 7-8

Both PEDA and APPL appealed this order

Source reference: p. 8
02

Issues

1. Whether the construction of the Escape Channel constitutes a Force Majeure event warranting the addition of its cost to the capital cost for tariff re-determination.

Source reference: p. 23

2. Whether PEDA is liable to compensate APPL for the cost of the Escape Channel despite Clause 15 of the Tripartite Agreement.

Source reference: p. 27

3. Whether the State Commission acted within its jurisdiction under Section 86(1)(a) of the Electricity Act, 2003, by adjusting compensation against PEDA’s energy share.

Source reference: p. 31

4. Whether APPL is entitled to additional compensation for interest, O&M expenses, and carrying costs during the project shutdown.

Source reference: p. 33
03

Law Applied

The court applied Section 86(1)(a) of the Electricity Act, 2003, which empowers the State Commission to determine the tariff for generation and supply

Source reference: p. 31

It relied on the principle of "economic duress," holding that contracts signed under financial vulnerability and dominant bargaining positions may be reviewed for equity

Source reference: p. 29

The court further applied administrative law principles regarding tender transparency, asserting that an inviting agency is bound by the technical assurances (e.g., water discharge) provided in bid documents

Source reference: p. 26

It also cited Gujarat Urja Vikas Nigam Ltd. v. Essar Power Limited to affirm the Commission's jurisdiction over such disputes

Source reference: p. 18
04

Reasoning

The Tribunal found that the inability of the Holy Bein to handle 350 cusecs was not a Force Majeure event but a failure of due diligence by PEDA during the bidding stage

Source reference: p. 26

Consequently, while the generic tariff could not be re-determined as it was part of a competitive bid process, APPL deserved compensation for unforeseen infrastructure costs

Source reference: p. 26, 31

The Tribunal observed that APPL signed the TPA under "economic duress" while its plant was shut down, meaning Clause 15 did not bar compensation

Source reference: p. 29

PEDA, having derived a commercial advantage (the energy share) based on a flawed technical premise, was held liable

Source reference: p. 31

The Tribunal rejected PEDA’s argument that APPL could be compensated via "20% extra generation," noting that machines designed for 350 cusecs cannot safely or efficiently produce extra power simply by increasing water flow

Source reference: p. 32-33

Finally, the Tribunal held that while the principal cost was recoverable, APPL could not claim interest or O&M expenses as it had not timely protested the costs post-TPA

Source reference: p. 34
05

Holding

The Tribunal upheld the PSERC order with modifications.

Tariff re-determination is denied

Source reference: p. 26

APPL is entitled to the actual cost of the Escape Channel (without interest)

Source reference: p. 35

This cost must be adjusted against PEDA’s energy share

Source reference: p. 35

PEDA cannot transfer its share to PSPCL until APPL is fully compensated

Source reference: p. 35

The matter was remanded to PSERC to conduct a "prudence check" to finalize the actual construction costs incurred by APPL

Source reference: p. 34-35

All pending applications were disposed of

Source reference: p. 35
APTEL

Original Court PDF

PUNJAB ENERGY DEVELOPMENT AGENCY (PEDA)vsPUNJAB STATE ELECTRICITY REGULATORY COMMISSION (PSERC) & Ors

APTEL · March 24, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment