01Facts
The Appellants’ lands were acquired for National Highway construction under the National Highways Act, 1956 (Highways Act), following a notification dated September 3, 2009.
¶ 5While the land valuation was undisputed, the Appellants raised claims for 30% solatium under the Land Acquisition Act, 1894 (1894 Act) during the arbitral proceedings.
¶ 9-10The Arbitral Tribunal, in its award dated January 6, 2018, failed to grant solatium.
¶ 10The Appellants challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 (the Act), but the District Judge rejected the claim, holding that granting solatium would constitute an impermissible modification of the award.
¶ 11The Appellants then approached the High Court under Section 37 of the Act.
02Issues
i.1. Whether the court, under Section 37 of the Arbitration and Conciliation Act, 1996, has the authority to direct the correction of a computation regarding statutorily mandated solatium.
¶ 3ii.2. Whether the denial of solatium for land acquisition notified after March 28, 2008, constitutes a patent illegality or a correctable computational error.
¶ 14, 1803Law Applied
The court applied Section 3G and 3J of the National Highways Act, 1956, as interpreted through judicial precedents.
¶ 4It relied on Golden Iron and Steel Forging v. Union of India, which struck down the exclusion of solatium as discriminatory under Article 14.
¶ 5It relied on Sunita Mehra v. Union of India, which established March 28, 2008, as the cut-off date for solatium entitlement.
¶ 6The court applied Union of India v. Tarsem Singh, confirming solatium is payable for highway acquisitions.
¶ 7The court utilized the Constitution Bench ruling in Gayatri Balasamy v. ISG Novasoft Technologies Ltd., which held that courts under Section 34 can rectify computational, clerical, or typographical errors that do not require merits-based evaluation.
¶ 12Provisions in the judgment · 4
Arbitration And Conciliation Act, 1996 Section 31, 33, 34, 37
National Highways Act, 1956 Section 3G, 3J
Land Acquisition Act, 1894 Section 23, 28
Right To Fair Compensation And Transparency In Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 105, 113
04Reasoning
The court reasoned that since the acquisition notification was issued in 2009—well after the cut-off date established in Golden Iron and Steel and confirmed in Sunita Mehra—the Appellants were legally entitled to solatium.
¶ 10The court distinguished the present case from Sumanbai Bachchav, noting that here, the Appellants had expressly raised the issue of solatium before the Arbitral Tribunal.
¶ 16-17Applying Gayatri Balasamy, the court found that since there was no dispute regarding land valuation or classification, the 30% solatium was a purely mathematical addition to the existing compensation.
¶ 11, 21Therefore, the denial of solatium was a "computational error" and a "patent illegality" that the Section 34 court failed to correct, justifying intervention under Section 37.
¶ 21-2305Holding
The court answered the issues in the affirmative, holding that the addition of solatium constitutes a rectifiable computational error when the legal entitlement is crystallized.
¶ 22The High Court allowed the appeals, set aside the lower court’s refusal, and modified the awards to include 30% solatium under Section 23(2) of the 1894 Act. The Respondents were directed to compute and pay the modified amount within twelve weeks.
¶ 24, 25Original Court PDF
Prashant Vasant Koregaonkar And Ors.vsCompetent Authority Through Deputy Collector And Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
