Facts
The Petitioner, an infrastructure company, participated in a tender issued by the National Highways Authority of India (NHAI) on 23.01.2026 for the construction of a section of the Vadodara-Mumbai Expressway.
Source reference: p. 1-3On 25.06.2026, NHAI declared the Petitioner’s technical bid "Non-Responsive".
Source reference: p. 4The sole reason for rejection was the Petitioner’s failure to submit a "Provisional Completion Certificate" (PCC) alongside its Experience Certificate, as required by Clause 2.2.2.2(ii) and Annexure-IX of the Request for Proposal (RFP).
Source reference: p. 5-8The Petitioner contended that the Experience Certificate, issued by the client (MSRDC), already contained all material information typically found in a PCC, making the requirement a mere duplication.
Source reference: p. 9During the proceedings, the Petitioner obtained and furnished the PCC dated 30.06.2026.
Source reference: p. 9-12Issues
1. Whether the non-submission of a Provisional Completion Certificate (PCC), when the requisite information was already contained in a valid Experience Certificate issued by the same client, justified declaring the bid "Non-Responsive"
Source reference: p. 11 / para. 162. Whether the subsequent submission of the PCC before the opening of financial bids cured the technical deficiency
Source reference: p. 16 / para. 25Law Applied
The Court examined Clause 2.2.2.2(ii) of the RFP regarding "Technical Capacity," which mandates the submission of an Experience Certificate in a specific format (Annexure-IX) along with a PCC or CC.
Source reference: p. 6-8The Court applied the principle from S and P Infrastructure Developers Pvt. Ltd. v. National Highways Authority of India [2026 SCC OnLine Del 4384], which cautions against a "hyper-technical approach" in tender evaluations where substantive requirements are met.
Source reference: p. 10, 16It distinguished Central Coalfields Limited and Anr. v. SLL-SML (Joint Venture Consortium) and Ors. [(2016) 8 SCC 622], noting that while employers can insist on strict compliance with essential terms, such terms must serve a substantive purpose.
Source reference: p. 10, 16Reasoning
The Court compared the Experience Certificate dated 17.04.2026 with the PCC dated 30.06.2026 and found them to be functionally identical, with the Experience Certificate providing even more detailed information.
Source reference: p. 12-14The Court reasoned that since the Experience Certificate was not a self-declaration but a document issued by the client (MSRDC), its authenticity was not in doubt, rendering the insistence on a separate PCC a "duplication exercise".
Source reference: p. 14-15The Court observed that because MSRDC had not actually issued the PCC until requested during litigation, the Petitioner could not have submitted a non-existent document at the time of the bid.
Source reference: p. 16Applying the law, the Court held that the "essential requirement" of proving technical capacity was substantially complied with, and rejecting the bid for a missing corroborative document that adds no new information was arbitrary and hyper-technical.
Source reference: p. 15-17Holding
The Court answered the issues in the affirmative for the Petitioner, holding that the bid was wrongly declared non-responsive.
The Court set aside the Technical Evaluation result dated 25.06.2026.
Source reference: p. 17It ruled that the deficiency, if any, stood cured by the submission of the PCC dated 30.06.2026 before the opening of financial bids.
Source reference: p. 16The Court directed NHAI to evaluate the Petitioner's technical bid in light of the now-submitted PCC and consider its financial bid alongside other qualified bidders to enhance market competitiveness and serve the public interest. Writ petition allowed.
Source reference: p. 17, 18Original Court PDF
Roadway Solutions India Infra LimitedvsUnion Of India & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in