Facts
The Food Corporation of India invited a tender for transportation of food grains from RTC Kargi Road to Latehar, in which the petitioner was the successful bidder and was awarded the work order.
Source reference: para. 4A penalty was subsequently imposed on the petitioner. The petitioner challenged the penalty by submitting a representation/dispute before the Grievance Redressal Committee (“GRC”).
Source reference: para. 4However, the dispute was forwarded to the General Manager, who passed an order dated 25.11.2021, following an earlier communication/order dated 12.08.2021 issued by the Assistant General Manager (Contract), Zonal Office (West), Mumbai.
Source reference: paras. 1, 4The petitioner sought quashing of these orders and a direction to the GRC to adjudicate the dispute on merits.
Source reference: para. 1The petitioner relied on the decision in WPC No. 4588 of 2021, involving the same parties and an identical issue, and the respondents did not oppose disposal of the petition on the same terms.
Source reference: paras. 2–3Issues
Whether the General Manager was competent to decide the petitioner’s representation/dispute under Condition XI of the tender, or whether exclusive jurisdiction lay with the GRC.
Source reference: para. 4Whether the orders/communications dated 12.08.2021 and 25.11.2021 were liable to be quashed and the dispute remitted to the GRC for decision on merits.
Source reference: para. 4Law Applied
The Court applied Condition XI of the tender, which designated the Grievance Redressal Committee as the competent authority to consider and decide disputes arising under the contract.
Source reference: para. 4The Court held that an authority lacking jurisdiction under the tender conditions cannot adjudicate the contractor’s representation, and that a dispute must be decided by the authority contractually designated for that purpose.
Source reference: para. 4The Court also followed its earlier decision in WPC No. 4588 of 2021, decided on 03.11.2025, which concerned the same grievance and relief.
Source reference: paras. 2, 4Reasoning
The petitioner’s grievance related to a penalty imposed under the transportation contract. Although the petitioner had submitted the dispute to the GRC, the matter was forwarded to the General Manager, who proceeded to decide it.
Source reference: para. 4On examining Condition XI, the Court found that the GRC alone was competent to determine such a representation; therefore, the General Manager’s consideration of the dispute was contrary to the contractual allocation of authority.
Source reference: para. 4Since the issue was identical to that decided in the earlier case, and the respondents did not contest the petitioner’s submission, the Court applied the earlier ruling and directed that the dispute be considered afresh by the competent GRC.
Source reference: paras. 2–4Holding
The writ petition was disposed of in terms of the Court’s earlier decision.
The communication/order dated 12.08.2021 and the order dated 25.11.2021 were quashed.
Source reference: para. 4The matter was remitted to the respondent GRC to decide the petitioner’s representation in accordance with law, preferably within 60 days from the date of receipt or submission of a copy of the order.
Source reference: para. 4No order was made as to costs.
Source reference: para. 5Original Court PDF
M/S. TAMANNA ROAD CARRIERvsFOOD CORPORATION OF INDIA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
