Facts
The Appellant, a transmission licensee, developed a project on a Build, Own, Operate, Maintain, and Transport (BOOT) basis under a Transmission Service Agreement (TSA) dated 20 January 2012
Source reference: p. 3Due to delays, a supplementary TSA was executed on 9 June 2018
Source reference: p. 4The Appellant filed Petition No. 1328 of 2018 before the Uttar Pradesh Electricity Regulatory Commission (UPERC) seeking tariff payments from July 2017
Source reference: p. 4On 12 July 2018, the Commission passed an interim order directing payments to commence from 27 October 2017
Source reference: p. 5The Appellant subsequently filed an "additional statement of facts" requesting a revision of the effective date to 27 July 2017
Source reference: p. 5The Commission, vide the impugned order dated 13 December 2018, rejected these additional submissions and maintained the interim order
Source reference: p. 6-7Although the Commission's records marked the petition as "Disposed," no final hearing on the merits of the entire petition had occurred
Source reference: p. 9Issues
1. Whether the order dated 13 December 2018 constitutes a final order or an interlocutory order
Source reference: p. 9-102. Whether an appeal against an order rejecting a request for review or modification of an interim order is maintainable
Source reference: p. 12Law Applied
The Tribunal primarily applied the principles governing the nature of judicial orders, distinguishing between interlocutory and final orders based on the "tone, tenor, and circumstances" of the decision
Source reference: p. 10It relied on Order 47 Rule 7 of the Code of Civil Procedure (CPC), 1908, which stipulates that an order rejecting an application for review is not appealable
Source reference: p. 12The Tribunal further observed that the status of a case in administrative records (e.g., marked as "Disposed") does not override the legal character of the order if the underlying petition was never adjudicated on its merits
Source reference: p. 12Reasoning
The Tribunal analyzed the language of the impugned order and found that the Commission had effectively treated the Appellant’s "additional statement of facts" as a review petition
Source reference: p. 10The Tribunal noted that the Commission followed an "unusual course" by rejecting the prayer for modification without formally concluding the main petition
Source reference: p. 11It held that because the order merely stated that the interim directions of 12 July 2018 "will continue," it was inherently interlocutory and lacked the finality required to dispose of the petition
Source reference: p. 11-12Furthermore, the Tribunal reasoned that since the Appellant failed to challenge the original interim order of 12 July 2018, an appeal against a subsequent refusal to modify that order was legally impermissible under the CPC principles
Source reference: p. 13The Tribunal concluded that the Commission’s administrative marking of the case as "Disposed" was a clerical error, as the petition’s core claims remained unadjudicated
Source reference: p. 12Holding
The Tribunal held that the appeal is not maintainable as it was filed against an order rejecting a review/modification of an interlocutory order
The appeal was dismissed
Source reference: p. 14However, the Tribunal found that the Commission erroneously treated the original Petition No. 1328 of 2018 as disposed
Source reference: p. 13Consequently, the Tribunal directed the Commission to restore the petition to its docket, afford the parties a reasonable hearing, and pass a final order on the merits within two months
Source reference: p. 13The parties were granted liberty to approach the Tribunal again following the final disposal by the Commission
Source reference: p. 14Original Court PDF
South East U.P. Power Transmission Company LimitedvsUttar Pradesh Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in