Madras High Court
Administrative and Public LawCivil Law

Outstanding electricity-supply dues must be adjusted against consumption and demand charges before disconnection.

V.S.M. Weavess India (Pvt) Ltd vs Tamilnadu Electricity Regulatory Commission,

Madras High CourtJUDGMENT: September 30, 20262 MIN READSOURCE JUDGMENT
Outstanding electricity-supply dues must be adjusted against consumption and demand charges before disconnection.. V.S.M. Weavess India (Pvt) Ltd vs Tamilnadu Electricity Regulatory Commission,. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner sought a mandamus restraining the respondents from collecting current-consumption charges, demand charges, or arrears until they paid or adjusted ₹13,31,700 allegedly due for electricity supplied during 2025–2026.

Source reference: p.2

At admission, both sides informed the Court that similar petitions had been disposed of on terms providing for adjustment of amounts due to the petitioner against its electricity charges and protection against disconnection while adjustment remained incomplete.

Source reference: pp.2–5
02

Issues

1. Whether the respondents should be directed to adjust the ₹13,31,700 allegedly due to the petitioner against its current-consumption and demand charges.

Source reference: pp.2, 5

2. Whether the respondents should be restrained from taking coercive steps to disconnect the petitioner’s electricity supply until the amount due is fully adjusted.

Source reference: p.5
03

Law Applied

Exercising its jurisdiction under Article 226, the Court followed the approach in M/s. Rajaguru Spinning Mills P. Ltd. v. Tamil Nadu Electricity Regulatory Commission, as applied in earlier writ petitions, including W.P. No. 38309 of 2024.

Source reference: pp.3–5

Under that approach, amounts due to a petitioner may be adjusted against its current-consumption or open-access charges until exhausted, and the electricity connection should not be disconnected while that adjustment is pending.

Source reference: pp.3–5
04

Reasoning

The Court treated the matter as covered by prior decisions involving the same issue.

Source reference: pp.2–5

Relying on the terms reproduced from those decisions, it disposed of the petition on the same basis, directing adjustment of the amount due against the petitioner’s current-consumption and demand charges and protection against disconnection until the amount was exhausted.

Source reference: pp.2–5

The judgment does not separately examine or make an express finding on the disputed amount of ₹13,31,700.

Source reference: pp.2–5
05

Holding

The writ petition was disposed of on the same terms as the earlier orders: the amount due to the petitioner is to be adjusted against its current-consumption and demand charges, and the respondents are not to take coercive steps to disconnect the petitioner’s electricity supply until the outstanding amount is fully adjusted.

The connected miscellaneous petition was closed, with no order as to costs.

Source reference: p.5
Madras High Court

Original Court PDF

V.S.M. Weavess India (Pvt) LtdvsTamilnadu Electricity Regulatory Commission,

Madras High Court · September 30, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment