Madras High Court
Administrative and Public LawCommercial and Corporate Law

Wheeling agreements must provide 75% compensation for surplus solar energy under the tariff order.

Prabhu Textiles vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High CourtJUDGMENT: October 01, 20262 MIN READSOURCE JUDGMENT
Wheeling agreements must provide 75% compensation for surplus solar energy under the tariff order.. Prabhu Textiles vs TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners sought revision of clauses in their Energy Wheeling Agreements which, they contended, were inconsistent with paragraph 5.5.8 of the Tamil Nadu Electricity Regulatory Commission’s Solar Tariff Order No. 9 of 2020.

Source reference: p. 3–6

They sought payment for unutilised surplus solar energy at 75% of the competitively discovered tariff, stated to be ₹3.04 per unit.

Source reference: p. 3–6

The Court was referred to earlier writ orders directing revision of similar agreement clauses in light of the Commission’s order in M.P. No. 47 of 2021, dated 11 May 2023.

Source reference: p. 7–10

The respondents submitted that an appeal against the Commission’s order was pending before APTEL.

Source reference: p. 10–11
02

Issues

1. Whether the respondents should be directed to revise the petitioners’ Energy Wheeling Agreement clauses to conform to paragraph 5.5.8 of Solar Tariff Order No. 9 of 2020 and settle amounts payable for surplus energy.

Source reference: p. 3–6, 10–11

2. Whether compliance with those directions should await the outcome of the appeal pending before APTEL.

Source reference: p. 10–11
03

Law Applied

Article 226 of the Constitution empowers the High Court to issue appropriate writs, including mandamus.

Source reference: no citation

Paragraph 5.5.8 of Solar Tariff Order No. 9 of 2020, as considered by the Commission in M.P. No. 47 of 2021, provides for payment for energy supplied over and above the sanctioned limit at 75% of the tariff fixed by the Commission or, where no tariff is fixed, at 75% of the tariff discovered through competitive bidding; the Commission also found the inconsistent agreement clause contrary to the tariff order and Regulation 7 of the Power Procurement from New and Renewable Sources of Energy Regulations, 2008.

Source reference: p. 8–9

The Court followed its earlier orders in W.P. No. 31457 of 2025 and W.P. No. 49777 of 2025, which had directed amendment of similar agreements.

Source reference: p. 7–10
04

Reasoning

The Court treated the issue as covered by its earlier decisions, which had relied on the Commission’s finding that inconsistent agreement terms could not displace the applicable tariff order.

Source reference: p. 7–10

Applying that approach, it directed the respondents to revise the relevant clauses in the petitioners’ agreements and to settle any amount payable after modification.

Source reference: p. 11

Although an appeal was pending before APTEL, the Court held that the respondents need not defer compliance; they could proceed in accordance with law after APTEL decides the matter.

Source reference: p. 10–11
05

Holding

The writ petitions were disposed of with a direction to respondents 2 to 4 to revise the relevant agreement clauses by incorporating paragraph 5.5.8 of the tariff order within six weeks from uploading of the web copy.

Any amount found payable is to be settled within eight weeks thereafter.

Source reference: p. 11

Compliance is not to await APTEL’s decision, but the authorities may act in accordance with law once that decision is made.

Source reference: p. 11

No costs were ordered.

Source reference: p. 11
06

Acts & Sections Cited

6 provisions across 5 statutes referred to in this judgment. Linked provisions open on LawLens.

Solar Tariff Order No. 9 of 2020 dated 16.10.2020 (Order No.9/20, passed in T.A.No.9 of 2020)1

Section 5.5.8

Energy Wheeling Agreement dated 25.02.2026 (SPG No.069514430159)1

Section 9

Energy Wheeling Agreement dated 13.03.20261

Section 7

Energy Wheeling Agreement dated 31.03.20222

Section 5Section 6

Energy Wheeling Agreement dated 03.03.20211

Section 24
Madras High Court

Original Court PDF

Prabhu TextilesvsTAMIL NADU ELECTRICITY REGULATORY COMMISSION

Madras High Court · October 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment