Facts
The petitioner sought a direction preventing the respondents from collecting current-consumption charges, demand charges, or arrears in respect of its HTSC No. 039094350323 until payment or adjustment of Rs. 81,529 allegedly due for unutilised energy generated by its wind energy generator under HTSC No. 079204721073, together with interest at 1% per month
Source reference: p. 2At the hearing, counsel for both sides submitted that the issue was covered by prior orders, including the order in W.P. No. 5623 of 2025, which in turn followed earlier decisions concerning adjustment of amounts payable for energy supplied and protection against disconnection while adjustment was pending
Source reference: pp. 3–5Issues
1. Whether the petitioner was entitled to have the amount due for unutilised energy generated by its wind energy generator adjusted against its current-consumption and demand charges
Source reference: pp. 2–32. Whether the respondents could take coercive steps to disconnect the petitioner’s electricity supply before the amount due was fully adjusted
Source reference: pp. 4–5Law Applied
That approach provides that, where amounts are payable by the electricity distribution utility for energy supplied by a consumer, adjustment may continue against the consumer’s current-consumption or open-access charges until the amount is exhausted, and the utility should not disconnect the consumer’s supply while that adjustment remains pending
Source reference: pp. 4–5The Court also followed the orders in W.P. No. 38309 of 2024 and W.P. No. 5623 of 2025, which applied that approach to similar disputes
Source reference: pp. 3–5Reasoning
The Court did not undertake a separate examination of the amount claimed or the petitioner’s entitlement on the merits.
Source reference: pp. 3, 5Because both sides accepted that the issue was covered by prior decisions, the Court followed the established adjustment and non-disconnection approach, directing disposal on the same terms as the cited orders
Source reference: pp. 3, 5The judgment does not expressly state that the claimed interest at 1% per month is to be included in the adjustment.
Source reference: no citationHolding
Accordingly, the respondents were to adjust the amount payable to the petitioner against its current-consumption and demand charges until exhausted and not take coercive steps to disconnect its electricity supply while the outstanding amount remained to be adjusted
The writ petition was disposed of on the same terms as the cited precedents, with no order as to costs; the connected miscellaneous petition was closed
Source reference: p. 5Original Court PDF
Sri Marudhamalai Andavar Spinning MillsvsTamil Nadu Power Distribution
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
