01Facts
The complainant alleged that he paid ₹30 lakh to M/s Shri Shyam Sunder Developers Pvt. Ltd. for a plot in a proposed township.
pp. 2–3, 5After the company failed to develop the township and allot the plot, petitioner Mahipal Singh, its director and authorised signatory, issued a cheque for ₹30 lakh.
pp. 2–3, 5The cheque was dishonoured for insufficient funds, and the complainant’s demand notice was not followed by payment.
pp. 2–3, 5The trial court convicted the petitioner under Section 138 of the Negotiable Instruments Act, 1881, and imposed two years’ rigorous imprisonment and compensation of ₹30 lakh; the appellate court upheld the conviction and sentence.
pp. 1–2The petitioner filed a revision 757 days late; the High Court condoned the delay and considered the revision on its merits.
p. 102Issues
i.Whether the 757-day delay in filing the revision petition should be condoned.
p. 1ii.Whether the cheque represented a legally enforceable debt or liability, despite the petitioner’s contention that the underlying amount had become time-barred.
pp. 5–6iii.Whether the concurrent conviction and sentence disclosed any illegality, impropriety, or perversity warranting interference in revision.
pp. 4, 6–703Law Applied
Section 5 of the Limitation Act permits condonation of delay for sufficient reasons; the Court allowed the application on the reasons stated in it.
p. 1Section 138 of the Negotiable Instruments Act applies where a cheque is drawn on an account for discharge of a debt or liability, is presented within its validity, is dishonoured for a specified reason, and the drawer fails to pay within 15 days of receiving a written demand notice.
pp. 4–5The Court also stated that revisional jurisdiction under Section 397 Cr.P.C. is supervisory and is not a general power to reappreciate evidence; interference is warranted for material legal or procedural error, unsupported or perverse findings, or a gross miscarriage of justice.
p. 4Relying on M/s Maharia Automobiles v. Anil Kumar, CRA-AS-249-2023, the Court further stated that a cheque drawn for a time-barred debt may itself create an enforceable promise or contract.
p. 6Provisions in the judgment · 5 · Linked ones open on LawLens
Limitation Act, 1963 Section 5
Negotiable Instruments Act, 1881 Section 138
Code of Criminal Procedure, 1973 Section 313Section 357Section 397
04Reasoning
The petitioner admitted his signatures on the cheque, and the record established timely presentation, dishonour for insufficient funds, service of the demand notice, and non-payment.
p. 5The complainant’s evidence supported payment of ₹30 lakh to the company for the plot; the Court considered the company’s own records relevant to rebutting that evidence, and held that the complainant’s failure to specify the payment details or mode was not fatal.
pp. 5–6It rejected the time-barred-debt defence, reasoning that the cheque was issued after the company failed to develop the township and was intended to discharge the existing liability; it also applied the principle that a cheque for a time-barred debt can create an enforceable promise.
p. 6Finding no material error in the concurrent factual findings or procedure, the Court saw no basis for revisional interference.
pp. 6–705Holding
The Court condoned the 757-day delay, but dismissed the revision petition on the merits.
pp. 1, 6–7It upheld the petitioner’s conviction under Section 138 of the Negotiable Instruments Act and the sentence of two years’ rigorous imprisonment with compensation of ₹30 lakh, finding no illegality, impropriety, or perversity in the lower courts’ decisions.
pp. 1, 6–7Original Court PDF
Mahipal SinghvsRanbir Singh And Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in