Patna High Court
Civil Procedure and EvidenceProperty and Real Estate Law

Parallel writ proceedings cannot continue when civil suits over the same tenancy dispute remain pending.

M/s. Shiv Shanti Enterprises vs The State of Bihar

Patna High CourtJUDGMENT: August 20, 20263 MIN READSOURCE JUDGMENT
Parallel writ proceedings cannot continue when civil suits over the same tenancy dispute remain pending.. M/s. Shiv Shanti Enterprises vs The State of Bihar. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner had occupied a 2,644 sq. ft. shop on the ground floor of Udyog Bhawan, popularly known as Apna Bazar, under successive rent agreements with the Bihar Industrial Area Development Authority (“BIADA”) since 2008.

Source reference: para. 4

The last renewal extended the tenancy from 4 October 2021 to 3 October 2024.

Source reference: para. 4

BIADA subsequently issued a notice dated 27 May 2022 requiring the petitioner to vacate within three months under Clause 5 of the rent agreement, which permitted termination by either party upon three months’ written notice.

Source reference: paras. 5–6

The petitioner instituted Title Suit Nos. 302 of 2022 and 398 of 2022 and sought interim protection against dispossession; the injunction application was rejected on 2 March 2023.

Source reference: para. 6

BIADA thereafter issued notice dated 13 March 2023 requiring removal of the alleged encroachment by 27 March 2023.

Source reference: para. 6

The petitioner challenged the notice under Article 226 of the Constitution, contending that the Bihar Public Land Encroachment Act, 1956 (“Encroachment Act”) did not apply to a landlord–tenant dispute and that BIADA officials lacked jurisdiction to initiate encroachment proceedings.

Source reference: paras. 2, 11–12

The petitioner’s challenge to the rejection of interim relief was also pending before the competent civil court in Miscellaneous Civil Appeal No. 09 of 2023.

Source reference: paras. 8, 15
02

Issues

1. Whether BIADA could treat the petitioner’s occupation of the tenanted premises as an encroachment and initiate proceedings under the Bihar Public Land Encroachment Act, 1956.

Source reference: paras. 2, 11–12

2. Whether the BIADA officials who issued the impugned notice possessed jurisdiction under the Encroachment Act.

Source reference: para. 2

3. Whether the petitioner could pursue the writ petition while the title suits and proceedings concerning interim relief remained pending before the competent civil court.

Source reference: paras. 15–20

4. Whether the petitioner should be granted time to obtain appropriate relief from the civil court or vacate the premises.

Source reference: paras. 21–24
03

Law Applied

The Court considered the Bihar Public Land Encroachment Act, 1956, under which proceedings for removal of encroachment must be undertaken by the competent statutory authority and in accordance with due process.

Source reference: para. 2

It also considered the contractual termination provision in Clause 5 of the rent agreement, permitting either party to terminate the tenancy by giving three months’ prior written notice.

Source reference: paras. 5, 19

The Court relied upon Ashwani Kumar & Ors. v. State of Bihar & Ors., C.W.J.C. No. 8441 of 2022, which held that a landlord–tenant relationship cannot be terminated by forcible dispossession and that eviction must ordinarily follow due process of law, including an eviction decree or proceedings before the competent authority.

Source reference: paras. 10–10

The Court further applied the procedural principle that parallel proceedings should not be pursued where the same dispute is already pending before a competent civil court.

Source reference: paras. 16–20
04

Reasoning

The Court did not finally adjudicate the petitioner’s substantive challenges concerning the applicability of the Encroachment Act or the jurisdiction of BIADA’s officers.

Source reference: no citation

It noted that Clause 5 authorised termination of the tenancy by three months’ notice, while the petitioner had already invoked the jurisdiction of the civil court through title suits and an appeal concerning interim protection.

Source reference: para. 19

Since those proceedings remained pending, the Court held that parallel adjudication of the same dispute in the writ petition could not be permitted.

Source reference: para. 20

However, considering the parties’ long-standing landlord–tenant relationship since 2008, the petitioner’s request for time, and BIADA’s submission that the contractual notice period was three months, the Court granted a final period of 90 days to obtain appropriate relief from the competent civil court.

Source reference: paras. 21–24

The Court also noted that BIADA proposed renovation of the entire building and had not singled out the petitioner for eviction.

Source reference: para. 23
05

Holding

The writ petition was disposed of rather than decided on the merits.

The petitioner was granted 90 days from 20 August 2026 to obtain appropriate relief in the pending suit or Miscellaneous Civil Appeal No. 09 of 2023.

Source reference: para. 24

If no relief was obtained within that period, the petitioner was directed to vacate the premises immediately.

Source reference: para. 24

The Court clarified that the pendency of the writ petition would not prevent an amicable settlement and observed that, if the petitioner later participated in BIADA’s fresh letting process after renovation and satisfied the applicable criteria, he should receive appropriate weightage.

Source reference: para. 25

All pending interlocutory applications were also disposed of.

Source reference: paras. 26–27
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

Bihar Public Land Encroachment Act, 19562

Section 2Section 3
Patna High Court

Original Court PDF

M/s. Shiv Shanti EnterprisesvsThe State of Bihar

Patna High Court · August 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment