Karnataka High CourtAdministrative and Public LawProfessional Negligence and Discipline

Partial demolition of unauthorised construction negates inaction-based misconduct; disciplinary charges rightly quashed.

THE REGISTRARv.SRI RAGHAVENDRA M R

Partial demolition of unauthorised construction negates inaction-based misconduct; disciplinary charges rightly quashed.. THE REGISTRAR vs SRI RAGHAVENDRA M R. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Tribunal erred in quashing the enquiry entrustment order and articles of charge without examining whether Respondent No. 1 was negligent in performing his duty or whether his inaction amounted to misconduct.

The court held

The Court held that it cannot be said that no action was at all taken on the complaint.

It also directed

The Court declined to interfere with the Tribunal's order dated 11.06.2020, which quashed the enquiry entrustment and articles of charge against Respondent No. 1, and dismissed the writ petition.

The Court expressly disagreed with the Tribunal's findings on the alternate remedy under Section 8(1)(b) and on Section 9(5)(c), but did not set them aside, leaving these questions for determination in an appropriate proceeding.

01Facts

The Karnataka Lokayukta (Registrar and Additional Registrar of Enquiries) challenged the Karnataka State Administrative Tribunal's order dated 11.06.2020 in Application No. 1433/2018.

The Tribunal had quashed the enquiry entrustment order dated 23.06.2017 and the articles of charge dated 22.07.2017 against Respondent No. 1, an Executive Engineer (PWD, on deputation) with Mysuru City Corporation.

¶ 1

The complainant first complained to the BBMP Commissioner on 03.11.2014 about unauthorised construction, then approached the Lokayukta on 12.11.2014 alleging non-action.

¶ 5 · ¶ 9

The Lokayukta issued notice to Respondent No. 1 on 19.11.2014.

¶ 9

Respondent No. 1 conducted a spot inspection on 16.12.2014 and the compound wall was partly demolished on 20.12.2014.

¶ 5 · ¶ 9

A counter-complaint was lodged against the complainant on 22.12.2014.

¶ 5

The complainant filed a rejoinder on 10.02.2015 asserting that only a few feet of the wall had been demolished.

¶ 6

At the time of the action, Respondent No. 1 was an Assistant Executive Engineer.

¶ 9

Respondent No. 1 has since retired and his pensionary benefits were settled.

¶ 5

Respondent No. 2 (BBMP Commissioner) was deleted by order dated 13.11.2026.

02Issues

i.1. Whether the Tribunal erred in quashing the enquiry entrustment order and articles of charge without examining whether Respondent No. 1 was negligent in performing his duty or whether his inaction amounted to misconduct.

¶ 3 · ¶ 4

ii.2. Whether the complainant had an alternate remedy under Section 8(1)(b) of the Karnataka Lokayukta Act, 1984, and whether the Tribunal correctly construed Section 9(5)(c) of the Act.

¶ 3 · ¶ 8

iii.3. Whether Respondent No. 1 took any action on the complainant's grievance, such that the charge of non-action could be sustained.

¶ 5 · ¶ 6 · ¶ 9

03Law Applied

Section 8(1)(b) and Section 9(5)(c) of the Karnataka Lokayukta Act, 1984, concerning the complainant's alternate remedy and the Lokayukta's procedure, were relied upon but expressly not decided, being reserved for appropriate proceedings.

¶ 8

Section 321 of the Karnataka Municipal Corporations Act, 1976, was invoked for the proposition that responsibility for unauthorised construction rests not only on the Assistant Executive Engineer but also on the concerned Executive Engineer.

¶ 9

The Court exercised its discretion under Articles 226 and 227 of the Constitution of India, refusing interference on the peculiar facts of the present case.

¶ 7

No precedents were cited.

Provisions in the judgment · 3 · Linked ones open on LawLens

KARNATAKA (ABOLITION OF CASH GRANTS) ACT, 1967 Section 8Section 9

KARNATAKA MUNICIPAL CORPORATIONS ACT, 1976. Section 321

04Reasoning

The Court declined to rely on the Tribunal's reasoning on alternate remedy and Section 9(5)(c), stating it did not agree with those findings but would leave them open.

¶ 8

On the merits, the Court reconstructed the chronology: the complaint was lodged within nine days of the BBMP complaint, the Lokayukta issued notice, inspection followed, and partial demolition occurred within about five weeks.

¶ 9

Because Respondent No. 1 was then an Assistant Executive Engineer, the Court held he could not alone be held responsible, given the Executive Engineer's supervisory role under Section 321.

¶ 9

The complainant's rejoinder of 10.02.2015 did not negate the earlier action, since partial demolition was admitted and reflected in the material.

¶ 9

The Court noted the respondent's long retirement and advanced age as a factor against revival of proceedings.

¶ 9

The Court found no basis to disturb the Tribunal's quashing order on the facts, without deciding the statutory questions.

¶ 7-9

05Holding

The Court held that it cannot be said that no action was at all taken on the complaint.

¶ 9

The Court declined to interfere with the Tribunal's order dated 11.06.2020, which quashed the enquiry entrustment and articles of charge against Respondent No. 1, and dismissed the writ petition.

¶ 10

The Court expressly disagreed with the Tribunal's findings on the alternate remedy under Section 8(1)(b) and on Section 9(5)(c), but did not set them aside, leaving these questions for determination in an appropriate proceeding.

¶ 8
Karnataka High Court

Original Court PDF

THE REGISTRARvsSRI RAGHAVENDRA M R

Karnataka High Court · November 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment