Facts
The Petitioner (ONGC) awarded a lump-sum contract to the Respondent (Sapura) for the redevelopment of the Mumbai High South Field
Source reference: para. 2, 5Upon timely completion of the work, Sapura raised six claims for additional works/change orders. ONGC partially admitted two claims (Claims 1 & 2) but disputed the applicable rates and rejected the remaining four claims (Claims 3–6)
Source reference: para. 8A three-membered Arbitral Tribunal delivered a unanimous Award on May 4, 2024, rejecting one claim, partially allowing two, and fully allowing three
Source reference: para. 11ONGC challenged the Award under Section 34 of the Arbitration & Conciliation Act, 1996, primarily arguing that the contract was on a turnkey basis and the works fell within the original scope or were performed at the contractor's risk
Source reference: para. 15–21Issues
1. Whether the ground of "patent illegality" under Section 34(2A) is available to challenge an award arising out of an International Commercial Arbitration
Source reference: para. 352. Whether the Arbitral Tribunal’s interpretation of contractual rates (Annexure-C) over "actuals" for Claims 1 and 2 was plausible
Source reference: para. 50, 673. Whether the instructions regarding IDDS (Claim 4) and change in installation philosophy (Claim 3) constituted "Change Orders" beyond the scope of a lump-sum contract
Source reference: para. 82, 92, 1014. Whether the grant of standby charges for the SK900 vessel (Claim 5) was perverse due to alleged ignorance of vital evidence
Source reference: para. 110, 126Law Applied
The court applied Section 34 of the Arbitration and Conciliation Act, 1996, specifically Section 34(2A) which excludes "patent illegality" as a ground for setting aside awards in International Commercial Arbitrations
Source reference: para. 35, 41It relied on Ssangyong Engineering & Construction Co. Ltd. v. NHAI, which clarified that "public policy of India" is restricted to the "fundamental policy of Indian law" and excludes "perversity" or "patent illegality" for international awards
Source reference: para. 39, 40The court further referenced Associate Builders v. DDA and PSA Sical Terminals (P) Ltd. v. V.O. Chidambranar Port Trust regarding the limited scope of judicial interference in contractual interpretation by arbitrators
Source reference: para. 22, 42Reasoning
The Court first determined that as an International Commercial Arbitration, the Award could not be challenged on grounds of "patent illegality" or "perversity"
Source reference: para. 45Regarding Claims 1 and 2, the Court analyzed Clause 8.1.1.4 and Annexure-C, finding the Tribunal's decision to apply contractually agreed unit rates—rather than rates from a different (B-127) contract—to be a plausible interpretation
Source reference: para. 58–60, 68For Claim 3 (SCA Platform) and Claim 4 (IDDS), the Court noted ONGC’s own admissions in meeting minutes that certain works (like deck extensions) were "not envisaged in contract scope," thereby validating the Tribunal's finding of a "Change Order"
Source reference: para. 93, 101On Claim 5 (Standby Charges), although the Court observed that the Tribunal appeared to have ignored specific correspondence (letter dated Jan 13, 2017) regarding SIMOPs, it held that such "perversity" constitutes "patent illegality" under Section 34(2A), which is expressly unavailable for international awards. Thus, the Court was statutorily barred from interfering even if the finding appeared erroneous
Source reference: para. 128–130Holding
The Court dismissed the Arbitration Petition, upholding the Arbitral Award in its entirety. It held that: (i) patent illegality is not a valid ground for challenge in international commercial arbitrations
(ii) the Tribunal's interpretation of contractual rates and additional works was plausible and based on evidence/admissions; and (iii) even if a finding is allegedly perverse or ignores evidence, it cannot be set aside in an international award under the current restrictive legal framework of Section 34. No costs were awarded for the petition
Source reference: para. 60, 102, 130, 133Original Court PDF
Oil And Natural Gas Corporation LtdvsSapura Fabrication Sdn Bhd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in