01Facts
The petitioner alleged that the public road (Aam Rasta) recorded on Khata No. 282, Plot No. 2284, at Mauza Gansia, Gopalganj, had been encroached upon.
p. 2 · ¶ 2After his complaint, the District Public Complaint Redressal Officer, by order dated 17 June 2023, directed the Circle Officer, Manjha, to make an inquiry and measurement and, if encroachment was found, initiate proceedings and remove it in accordance with law.
p. 2 · ¶ 2The State respondents stated that proceedings under the Bihar Public Land Encroachment Act, 1956, had been initiated following a complaint and an Amin’s report, and that statutory notices and inquiry were underway.
p. 3 · ¶ 3The petitioner acknowledged that proceedings had commenced but contended they remained unconcluded.
p. 4 · ¶ 402Issues
i.Whether the High Court should intervene where proceedings to determine and address the alleged encroachment had been initiated but not concluded.
p. 4 · ¶ 4–6ii.Whether the authorities should be directed to conclude those proceedings within a specified period.
p. 5 · ¶ 703Law Applied
The proceedings were governed by the Bihar Public Land Encroachment Act, 1956, including the notice procedures under Sections 3 and 6(2), as identified in the respondents’ counter-affidavit.
p. 3 · ¶ 3The Court’s order proceeded on the basis that the authorities should complete the pending statutory process in accordance with law; it did not decide whether an encroachment existed or state any broader rule concerning the merits of such proceedings.
p. 5 · ¶ 7Provisions in the judgment · 2
Bihar Public Land Encroachment Act, 1956 Section 3Section 6
04Reasoning
The Court noted that proceedings under the 1956 Act had been initiated against the alleged encroachers but were still pending.
p. 4 · ¶ 4–6Since the statutory process had not concluded, the Court did not determine the encroachment allegation or order immediate removal. Instead, it directed the authorities to complete the pending proceedings expeditiously, preserving the statutory process.
p. 5 · ¶ 705Holding
The Court directed the respondent authorities to conclude the proceedings under the Bihar Public Land Encroachment Act, 1956, as expeditiously as possible and within three months from receipt or production of the order.
p. 5 · ¶ 7The writ petition was disposed of with that direction.
p. 5 · ¶ 7–8Original Court PDF
Ashesher ShuklavsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in