Patna High Court
Contract LawCivil Procedure and Evidence

Payment of work dues is contingent upon verification of the work actually completed.

The State of Bihar vs Evermore India Pvt. Ltd.

Patna High CourtJUDGMENT: August 10, 20263 MIN READSOURCE JUDGMENT
Payment of work dues is contingent upon verification of the work actually completed.. The State of Bihar vs Evermore India Pvt. Ltd.. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Evermore India Pvt. Ltd. claimed outstanding dues of ₹89,11,419 for construction work undertaken under the Bagmati Flood Management Scheme, Phase-V(a), pursuant to Work Order No. 634 dated 2 July 2021.

Source reference: p. 2, para. 1

It filed C.W.J.C. No. 8643 of 2023 seeking payment of the alleged admitted dues, release of funds, statutory interest, and protection against coercive action.

Source reference: p. 2, para. 1

The learned Single Judge disposed of the writ petition by directing the authorities to verify the work completed by the petitioner and to pay the amounts due for the completed work.

Source reference: p. 3, para. 2

The State appealed, contending that the direction to make payment was conditional upon prior verification and that the order had been misinterpreted in contempt proceedings.

Source reference: p. 3, para. 4

In the contempt proceeding, C.W.J.C. No. 3276 of 2025, the Court directed payment of the claimed dues by 11 September 2026 and required the personal appearance of senior officials.

Source reference: p. 3, para. 4
02

Issues

Whether paragraph 13 of the Single Judge’s judgment directed unconditional payment of the respondent’s claimed dues, or whether payment was subject to prior verification of the work completed?

Source reference: p. 3, para. 2; p. 4, para. 5

Whether the direction requiring personal appearance of the concerned State officials in the contempt proceeding should remain operative before completion of the verification process?

Source reference: p. 3, paras. 4–5; p. 4, para. 8
03

Law Applied

The Court applied the principle that a judicial direction must be construed by reading the operative portion of the order as a whole and giving effect to all its conditions.

Source reference: no citation

A direction to pay amounts due for completed work, where preceded by a direction to verify the work completed, is conditional upon such verification.

Source reference: p. 4, para. 5

The Court also applied the principle that contempt proceedings must enforce, and cannot enlarge or alter, the substantive directions contained in the original judgment.

Source reference: no citation
04

Reasoning

The Division Bench examined paragraph 13 of the Single Judge’s order, which directed the authorities to “verify the work completed” and thereafter “pay the amounts due” for the work already completed.

Source reference: p. 3, para. 2

It held that the payment direction could not be treated as an unconditional command to pay the entire amount claimed by the respondent.

Source reference: p. 4, para. 5

Rather, payment was to follow verification of the work allegedly executed.

Source reference: p. 4, para. 5

The State’s objection that it had not been given an effective opportunity to verify the work was therefore accepted.

Source reference: p. 4, para. 5

Since the contempt order appeared to require payment of the claimed amount and personal appearance without allowing completion of the verification exercise, the Bench directed that the State be permitted to conduct a joint verification and submit its report before the Contempt Court.

Source reference: p. 4, paras. 6–8
05

Holding

The appeal was disposed of by clarifying that paragraph 13 of the Single Judge’s judgment required verification of the work completed before payment of the amounts found due.

The State was granted liberty to issue written notice to Evermore India Pvt. Ltd. for joint verification and to submit the verification report before the Contempt Court on or before the next date fixed.

Source reference: p. 4, para. 6

If verification was not completed within the stipulated period, the State could seek appropriate directions from the competent court or authority.

Source reference: p. 4, para. 7

Until completion of verification, the direction requiring personal appearance of Opposite Party Nos. 1 and 2 was kept in abeyance.

Source reference: p. 4, para. 8

The appeal was accordingly disposed of.

Source reference: p. 5, para. 9
Patna High Court

Original Court PDF

The State of BiharvsEvermore India Pvt. Ltd.

Patna High Court · August 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment